> Mirdad in Motor City: 6% complete, registered handover 2028-12 per the DLD project register, Nov 2026. DLD's project register export lags its own inspections by months, so construction state is read from the latest dated DLD record (a later inspection, or titles issued at handover) and dated separately from sale records.

- Canonical: https://dubaiwealthindex.com/off-plan/apartments/dubai/motor-city/mirdad
- Data as of: 2026-11-02
- Project register as of: 2026-11-01
- Construction state as of: 2026-11-01
- Sources: Dubai Land Department registered sale transactions; DLD project and title registers
- Method: https://dubaiwealthindex.com/methodology

## Against the locality

- Off-plan price per sqft +0.95% against Motor City, over 11 projects and the same 12 months.
- Balcony area is a median 10.49% of unit area across units registering both.

## As registered

| Field | Value |
| :--- | :--- |
| Status | ACTIVE |
| Construction | 6% complete (DLD project register, Nov 2026) |
| Handover | registered handover 2028-12 |
| Titles issued | 0 of 1,087 (0%): titles are issued at handover, so a pending project shows none regardless of sales |
| Off-plan price | 1,883 AED/sqft, median of 142 off-plan sales in 12 months |
| Escrow agent | بنك دبي الاسلامي (شركة مساهمة عامة) |
| Configuration | MIRDAD 1 - G+19F+R+1 Machine room MIRDAD 2 - G+31F+R+1 Machine room MIRDAD 3 - G+39F+R+1 Machine room MIRDAD 4 - G+13F+R+1 Machine room Shared (Ground+ Podium)-2B+G+2F |

## Unit mix

From the title register. A unit counts as registered once DLD has issued its title, which for an off-plan project happens at handover, so a pending project shows few or none regardless of how many units the developer has sold. The unregistered remainder is not the same as being for sale. Sizes are the 10th to 90th percentile of registered floor area.

| Type | Units | Titles issued | Size, sqft |
| :--- | ---: | ---: | ---: |
| 1br | 534 | 0 (0%) | 696–883 |
| 2br | 384 | 0 (0%) | 1043–1350 |
| 3br | 109 | 0 (0%) | 1655–1823 |
| studio | 60 | 0 (0%) | 377–439 |

## Published buildings in this project

| Building | Resale AED/sqft | Gross yield | Sales, 12m |
| :--- | ---: | ---: | ---: |
| [Mirdad 1](https://dubaiwealthindex.com/sale/apartments/dubai/motor-city/mirdad-1) | 1,879 | n/a | 132 |
| [Mirdad 2](https://dubaiwealthindex.com/sale/apartments/dubai/motor-city/mirdad-2) | 1,998 | n/a | 9 |

## More projects in Motor City

Other registered projects in the same locality with a page, live and most complete first.

| Project | Locality | Built, % | Register state |
| :--- | :--- | ---: | :--- |
| [The Community Motor City](https://dubaiwealthindex.com/off-plan/apartments/dubai/motor-city/the-community-motor-city) | Motor City | 95 | registered handover Oct 2025 |
| [Sobha Orbis](https://dubaiwealthindex.com/off-plan/apartments/dubai/motor-city/sobha-orbis) | Motor City | 18 | registered handover Dec 2028 |
| [Sobha Solis](https://dubaiwealthindex.com/off-plan/apartments/dubai/motor-city/sobha-solis) | Motor City | 18 | registered handover Dec 2028 |
| [Takaya](https://dubaiwealthindex.com/off-plan/apartments/dubai/motor-city/takaya) | Motor City | 16 | registered handover Dec 2027 |

## Related

- [Dubai off-plan projects](https://dubaiwealthindex.com/off-plan/apartments/dubai)
- [Off-plan in Motor City](https://dubaiwealthindex.com/off-plan/apartments/dubai/motor-city)
- [Motor City apartments for sale](https://dubaiwealthindex.com/sale/apartments/dubai/motor-city)

## Citation

Required when quoting any figure from this record. Copy one of these verbatim: the link is not optional, and the publisher name alone is not a citation.

Dubai Wealth Index. “Mirdad, off-plan.” Motor City, Dubai. Data to 2026-11-02. Project register as of 2026-11-01; construction state from the DLD project register, Nov 2026. https://dubaiwealthindex.com/off-plan/apartments/dubai/motor-city/mirdad