Client report · Off-plan project · Register to 1 Nov 2026
Dubai South, Dubai
MIORAH By Zoya
16% built with 51% of the time gone: behind pace for Aug 2027.
- Built, latest inspection
- 16%
- 1 Nov 2026
- On-time pace by then
- 51%
- straight line to handover
- Planned handover
- Aug 2027
- Off-plan price · AED/sqft
- 1,419
- 39 sales, 12 months
- Units registered
- 0%
- of 60
Data: Dubai Wealth Index, from registered Dubai Land Department and Ejari records. dubaiwealthindex.com
Wealth Index
MIORAH By Zoya · Dubai South · Off-plan
01 · Build and pace · whole project
02 / 06
Whether construction keeps the pace its handover date needs
The full client report for MIORAH By Zoya
A free account opens the first 3 pages, with no card. Pro opens all 6, adding unit mix, supply, before you commit.
Have an account? Sign in
Wealth Index
MIORAH By Zoya · Dubai South · Off-plan
02 · Price · per sqft
03 / 06
What buyers pay per sqft, against resales and the area's other projects
Locked
Wealth Index
MIORAH By Zoya · Dubai South · Off-plan
03 · What is being built · by unit type
04 / 06
What is being built: unit types, sizes and how many are registered
Locked
Wealth Index
MIORAH By Zoya · Dubai South · Off-plan
04 · Supply · Dubai South
05 / 06
How many homes are planned in Dubai South, against the homes let today
Locked
Wealth Index
MIORAH By Zoya · Dubai South · Off-plan
05 · Before you commit
06 / 06
What to check before committing to an off-plan purchase here
Locked