International City LLC, delivery record

Edition DWI-DEVELOPER-INTERNATIONAL-CITY-LLC
Registered projects
33
DLD register, Jul 2026
Delivered on time
100%
of 15 completed
Median slippage
0months
registered date to recorded completion
Live and overdue
8
of 18 live

Every project the Dubai Land Department registers to انترناشونال سيتي ( ش.ذ.م.م ), which this site publishes as International City LLC — a high-confidence reading of the registered Arabic name. On-time delivery and slippage are measured on completed projects against the completion date the developer itself registered. A live project past that date is counted as overdue, not as late: it has not been delivered yet, and this site does not forecast when it will be.

Live projects

18 registered and not yet recorded complete, most advanced first.

Delivered projects

15 recorded complete, most recent first. Slippage is months from the registered date to the recorded one; negative is early.

ProjectLocalityRegisteredCompletedSlippage, months
Al Helal Al Zahaby 3International City Phase 3Aug 2023Aug 2023on time
Tabeer 1International CityJun 2022Jun 2022on time
Lawnz Residence by DanubeInternational CityFeb 2022Feb 2022on time
Suncity HomesInternational City Phase 3Feb 2021Feb 2021on time
BelvedereInternational CityOct 2022Jan 2021-21
Easy18International City Phase 3Jul 2019Jul 2019on time
Park ville 07International City Phase 3Mar 2019Mar 2019on time
Al Helal Al Zahaby 2International City Phase 3Mar 2019Mar 2019on time
Al Helal Al Zahaby BuildingInternational City Phase 3Oct 2017Oct 2017on time
Modelux Tower 1International City Phase 3Sept 2017Sept 2017on time
Indigo Spectrum 2International CityAug 2017Aug 2017on time
Dragon ViewInternational CityAug 2016May 2016-3
Indigo SPECTRUM1International CityApr 2015Apr 2015on time
EatonInternational City Phase 3Aug 2024Mar 2011-161
Global Green View IIInternational CityDec 2017Jun 2010-90

International City LLC, delivery record

Record type
Developer-level off-plan register record
Data date
Evidence base
33 registered projects, 15 completed; DLD project register as of 2026-07-06; identity high-confidence
Sources
Dubai Land Department project register
Canonical record
/developers/international-city-llc
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “International City LLC, delivery record.” Register to 2026-07-06, data to 2026-08-26. https://dubaiwealthindex.com/developers/international-city-llc.