Will Dubai’s off-plan projects finish on time?
141 of 852 dated live projects (17%) are already past their registered completion date. The median live project is 4.4% built.
Live projects past their date
17%
141 of 852 with a registered date
- Live projects
- 990
- Median built
- 4.4%
- Due within 12 months
- 291
- Areas
- 74
Every area, ordered by live projectsOf the eight busiest areas, Business Bay has the largest share past date (33%) and Dubailand Residence Complex the smallest (3%)
Share of live projects with a registered completion date that are past it · Showing 20 of 74 areas
Registered developers with 10 or more projectsOf their 418 live projects, 13% of those with a registered date are past it
Each developer’s whole register, apartments and villas, as on its own page. The registered developer is often the master developer of the land, not the builder of the tower.
Launch vs resale+19.6% median difference across 1,444 buildings in 69 areas
Survivors only, unpaired, before costs: each building’s all-time off-plan median price per sq ft against its ready resales in the last 12 months. Stock that never resold cannot appear, and the two legs are different buyers.
The top 20 of 1,444, from 250,317 registered launch sales (2004–2026) and 25,285 resales in the last 12 months. A top row is an outlier by construction.
Common questions
- How many Dubai off-plan apartment projects are past their completion date?
- 141 of 852 live off-plan apartment projects with a registered completion date (17%) are past it, measured against the Land Department register’s own date. 138 live projects carry no registered date. A date on file is the developer’s own promise, not a delivery forecast. Register dated 2026-07-06.
- Which Dubai areas have the most off-plan projects past their date?
- Of the eight areas with the most live projects, Business Bay has the largest share past its registered date (33%, 10 of 30) and Dubailand Residence Complex the smallest (3%, 2 of 65). Register dated 2026-07-06.
- Does the register show whether completed projects were delivered on time?
- Not reliably. 790 of 1,161 recorded completions in this cohort carry a completion date identical to the registered date, to the day: the register writes one onto the other, so no slippage is observable. That is why this page measures live projects past their date rather than an on-time rate. Register dated 2026-07-06.
- Which registered developer has the most live off-plan projects?
- Azizi Developments, with 47 live projects; 24% of its 42 dated live projects are past their registered date. The registered developer is often the master developer of the land, not the builder of the tower. Register dated 2026-07-06.
- How do Dubai launch and resale median prices compare?
- The median unpaired difference is +19.6% between each building's all-time median off-plan price and its trailing-12-month resale median, across 1,444 buildings in 69 areas that carry both legs, launched 2004–2026, from 250,317 launch sales and 25,285 ready resales in the last 12 months. These are different transaction groups before costs, not realised buyer gains. Data to 2026-10-12.
Source: Dubai Land Department project register and sale transactions. Sales to . Project register to .
Dubai off-plan apartment delivery record, by area
- Record type
- City-level off-plan delivery record
- Data date
- Evidence base
- 990 live off-plan apartment projects in 74 areas, 852 with a registered completion date; 1,444 buildings in the launch-vs-resale comparison
- Sources
- Dubai Land Department project register and sale transactions
- Canonical record
- /off-plan/apartments/dubai
Cite as: Dubai Wealth Index. “Will Dubai’s off-plan projects finish on time?” Project register to 2026-07-06, sales to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai