Will Dubai’s off-plan projects finish on time?

990 live projects · 74 areas · 852 with a registered completion date

141 of 852 dated live projects (17%) are already past their registered completion date. The median live project is 4.4% built.

Live projects past their date

17%

141 of 852 with a registered date

Live projects
990
Median built
4.4%
Due within 12 months
291
Areas
74

Every area, ordered by live projectsOf the eight busiest areas, Business Bay has the largest share past date (33%) and Dubailand Residence Complex the smallest (3%)

AreaLive projectsWith a datePast dateShare past date
Jumeirah Village Circle115992929%
Dubai Islands908767%
Dubailand Residence Complex696523%
Dubai South58551018%
Business Bay36301033%
Al Furjan3530413%
Jumeirah Village Triangle3022314%
Jumeirah Garden City2626623%
Maritime City231716%
Arjan2118633%
Majan2119211%
International City Phase 22020630%
Town Square201417%
Bukadra191300%
Dubai Hills Estate191600%
Dubai Sports City1917635%
Mina Rashid181417%
City of Arabia171500%
Jumeirah Lake Towers1715853%
Palm Jumeirah1614321%

Share of live projects with a registered completion date that are past it · Showing 20 of 74 areas

Registered developers with 10 or more projectsOf their 418 live projects, 13% of those with a registered date are past it

#Registered developerLive projectsWith a datePast dateShare past date
1Azizi Developments47421024%
2Samana Developers3729621%
3Emaar Properties252329%
4Binghatti Developers2423835%
5Imtiaz2120210%
6Object One211800%
7Damac Properties201800%
8Nshama201400%
9Danube Properties1911436%
10Mina Rashid181417%

Each developer’s whole register, apartments and villas, as on its own page. The registered developer is often the master developer of the land, not the builder of the tower.

Launch vs resale+19.6% median difference across 1,444 buildings in 69 areas

Survivors only, unpaired, before costs: each building’s all-time off-plan median price per sq ft against its ready resales in the last 12 months. Stock that never resold cannot appear, and the two legs are different buyers.

#BuildingLaunch AED/sqftResale AED/sqftDifference
1Bv Residences 2Jumeirah Bay Island3,39010,837+219.7%
2BEACH VISTA Tower 2Dubai Harbour1,2223,514+187.5%
3Bluewaters Residences 8Bluewaters Island2,4717,045+185.1%
4Villa MyraJumeirah Village Circle321904+181.4%
5CappadociaJumeirah Village Circle281787+180.4%
6Bluewaters Residences 4Bluewaters Island2,0705,754+177.9%
7Golden Mile 2Palm Jumeirah7902,083+163.6%
8PalladiumJumeirah Lake Towers5851,481+153.1%
9Bluewaters Residences 3Bluewaters Island2,1775,346+145.6%
10One at Palm JumeirahPalm Jumeirah3,7269,143+145.4%
11Bluewaters Residences 6Bluewaters Island2,2725,562+144.9%
12GrenlandDistrict 115151,243+141.4%
13Marina StarDubai Marina1,2553,000+139.0%
14Golden Mile 3Palm Jumeirah7981,890+136.9%
15Bluewaters Residences 7Bluewaters Island2,1434,982+132.5%
16Golden Mile 5Palm Jumeirah8812,036+131.2%
17Villa PeraJumeirah Village Circle341786+130.5%
18Marina Quay WestDubai Marina8912,046+129.7%
19Silverene Towers BDubai Marina1,0862,491+129.3%
20Gr PanoramaThe Greens1,0622,380+124.1%

The top 20 of 1,444, from 250,317 registered launch sales (2004–2026) and 25,285 resales in the last 12 months. A top row is an outlier by construction.

Common questions

How many Dubai off-plan apartment projects are past their completion date?
141 of 852 live off-plan apartment projects with a registered completion date (17%) are past it, measured against the Land Department register’s own date. 138 live projects carry no registered date. A date on file is the developer’s own promise, not a delivery forecast. Register dated 2026-07-06.
Which Dubai areas have the most off-plan projects past their date?
Of the eight areas with the most live projects, Business Bay has the largest share past its registered date (33%, 10 of 30) and Dubailand Residence Complex the smallest (3%, 2 of 65). Register dated 2026-07-06.
Does the register show whether completed projects were delivered on time?
Not reliably. 790 of 1,161 recorded completions in this cohort carry a completion date identical to the registered date, to the day: the register writes one onto the other, so no slippage is observable. That is why this page measures live projects past their date rather than an on-time rate. Register dated 2026-07-06.
Which registered developer has the most live off-plan projects?
Azizi Developments, with 47 live projects; 24% of its 42 dated live projects are past their registered date. The registered developer is often the master developer of the land, not the builder of the tower. Register dated 2026-07-06.
How do Dubai launch and resale median prices compare?
The median unpaired difference is +19.6% between each building's all-time median off-plan price and its trailing-12-month resale median, across 1,444 buildings in 69 areas that carry both legs, launched 2004–2026, from 250,317 launch sales and 25,285 ready resales in the last 12 months. These are different transaction groups before costs, not realised buyer gains. Data to 2026-10-12.

Source: Dubai Land Department project register and sale transactions. Sales to . Project register to .

Dubai off-plan apartment delivery record, by area

Record type
City-level off-plan delivery record
Data date
Evidence base
990 live off-plan apartment projects in 74 areas, 852 with a registered completion date; 1,444 buildings in the launch-vs-resale comparison
Sources
Dubai Land Department project register and sale transactions
Canonical record
/off-plan/apartments/dubai
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Will Dubai’s off-plan projects finish on time?” Project register to 2026-07-06, sales to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai