Developer delivery records

Every developer with ten or more registered Dubai projects, measured against the completion dates it registered itself.

Developers ranked
22 of 28
Register
2026-07-06
Live projects past their date
13%
44 of 331 live projects with dates · 87 without dates
Median slippage
-1 mo
137 measurable completions
Registered projects
929
28 developers
Completions with no measurable date
339
of 511 completed

A developer sets its own completion date when it registers a project with the Dubai Land Department. The ranking here compares that date with the register’s own as-of date on projects that have not finished: a live project past its registered date is overdue, which is a checkable fact about today rather than a forecast.

Completed projects are a weaker record, and the page says so rather than ranking on them. The register dates 339 of 511 completions to the registered day exactly — it writes the one date onto the other on completion — so no slippage is observable for them. Slippage below is measured over the 137 completions whose two dates genuinely differ, and every figure carries that sample.

Delivery record, ranked

Ranked by the share of live projects already past the completion date the developer registered, fewest first, among developers with at least 5 live projects. Ties break on the count overdue, then on live projects. Slippage is shown for completed projects whose registered and recorded dates differ, with that sample beside it, and needs 5 such completions to publish; “stamped” counts completions the register dated to the registered day exactly, where no slippage is observable.

Register
1Object One23210%—2Jul 2026
2Damac Properties37200%-12n=71710 stampedJul 2026
3Nshama35200%—159 stampedJul 2026
4Sobha32180%-1n=6148 stampedJul 2026
5Emaar Dubai South27170%—109 stampedJul 2026
6Dubai Hills Estate40150%-6n=92515 stampedJul 2026
7Island Oasis16140%—22 stampedJul 2026
8Dubai Creek Harbour24120%—1210 stampedJul 2026
9Deyaar Development3290%—2319 stampedJul 2026
10Citywalk Residential 12370%+7n=5169 stampedJul 2026
11Mina Rashid20187%1 of 14 dated—21 stampedJul 2026
12Emaar Properties113259%2 of 23 dated-3n=218865 stampedJul 2026
13Imtiaz312110%2 of 20 dated—104 stampedJul 2026
14Tiger Properties26917%1 of 6 dated+6n=51711 stampedJul 2026
15Iman15717%1 of 6 dated—86 stampedJul 2026
16Samana Developers433721%6 of 29 dated—63 stampedJul 2026
17Dubai South261322%2 of 9 dated—139 stampedJul 2026
18Ellington Properties331723%3 of 13 dated—1614 stampedJul 2026
19Azizi Developments1374724%10 of 42 dated+1n=239064 stampedJul 2026
20Binghatti Developers672435%8 of 23 dated+4.5n=84327 stampedJul 2026
21Danube Properties381936%4 of 11 dated-4n=61911 stampedJul 2026
22Reportage Properties131236%4 of 11 dated—11 stampedJul 2026
—Continental Lmd104——63 stampedJul 2026
—Jumeirah Hills103——73 stampedJul 2026
—Mdn100—0n=7102 stampedJul 2026
—Select Global173—+7n=5147 stampedJul 2026
—The Lagoons Phase One212—-7n=51914 stampedJul 2026
—The Palm Jumeirah104——63 stampedJul 2026

22 of 28 developers clear the 5-live-project floor and carry a rank. The rest keep their counts and read “—” where a share would mislead.

Common questions

Which Dubai developer is running most to schedule?
Object One, with none of its 18 live projects with dates past the completion date it registered. Only developers with at least 5 live projects are ranked, because a clean sheet across three projects is not a record. Dubai Land Department project register to 2026-07-06.
How many Dubai off-plan projects are past their registered handover date?
44 of 331 live projects with dates on this page — 13% — are past the completion date their own developer registered, as of the register's date. That is a fact about today, not a forecast of when they will finish. Dubai Land Department project register to 2026-07-06.
How is developer delivery measured here?
Against the completion date the developer itself registered with the Land Department. The ranking uses live projects only: a project that has not finished and whose registered date has passed is overdue, and no later record can revise that. Completed projects are a weaker record — the register dates 339 of them to the registered day exactly, so no slippage is observable — and slippage is therefore reported over the 137 completions whose two dates genuinely differ. Dubai Land Department project register to 2026-07-06.
When a Dubai project's delivery date can be measured, how late is it?
The median measurable completion finished 1 month before its registered date, over 137 completions; 63% of those landed on or before it. This sample excludes completions the register dated to the registered day, which cannot show slippage either way. Dubai Land Department project register to 2026-07-06.
Which Dubai developers have the most projects past their registered date?
Azizi Developments, with 10 of its 47 live projects past the date it registered. Dubai Land Department project register to 2026-07-06.

Source: Dubai Land Department project register, as of 2026-07-06. Dates are the developer’s own registrations, not forecasts. A completion the register dated to the registered day carries no observable slippage and is excluded from the slippage figures rather than counted as on time. A developer is the company licensed to build the project, by the licence number on its registration — not the master developer that owns the land — and each record states its identity confidence.

Dubai developer delivery records

Record type
Developer-level register record, ranked
Data date
Evidence base
28 developers, 929 registered projects, 418 live and 44 of those past their registered date, 137 completions with a measurable slippage; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register
Canonical record
/developers
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Dubai developer delivery records.” Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/developers