Off-plan · DLD project register as of 6 Jul 2026

DAMAC City

Under construction · 509 units · started Jun 2022 · Al Wasl

Registered for handover in Q4 2025 and 38% built in July 2026, 7 months past that date. Off-plan units sell at AED 2.90M (AED 2,232/sqft), 31% below the Al Wasl off-plan median.

Off-plan price, typical unit

2.90MAED

AED 2,232/sqft · 31% below Al Wasl off-plan · 51 sales in 12 months

Built38%

Started Jun 2022Registered handover Dec 2025 · overdue

DLD project register, Jul 2026

Median off-plan sale
AED 2.90M
Titles issued
0 of 509
Escrow
بنك الإمارات دبي الوطني (ش.م.ع)

Is DAMAC City a safe off-plan buy?In escrow; 38% built and 7 months past its registered handover; no record of the builder

  1. Is it on schedule?38% built in July 2026, 7 months past its registered December 2025 handover · DLD project register, Jul 202638%Context
  2. Is my money protected?Payments go to an escrow account at بنك الإمارات دبي الوطني (ش.م.ع), as registered with the Land DepartmentEscrowContext
  3. Is the price fair?AED 2,232/sqft, 30.7% below the Al Wasl off-plan median across 9 projects-30.7%Context
  4. Is it selling?51 off-plan sales registered in the last 12 months, of 509 units; the latest on 12 Oct 202651Context
  5. Who is building it?The register names the master developer, Meraas; the builder is not recordedNo record

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

How each reading works →

What is being built509 units, mostly two-beds and one-beds; none titled yet

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
1 bed205838–8390
2 bed2491,234–2,1700
3 bed452,109–4,1980
4+ bed102,860–9,0060

DLD unit register · balconies a median 17% of unit area · median off-plan sale AED 2.90M

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

509 units in DLD’s register for DAMAC City, floor by floor.

Show 400 of 509 units
FloorUnitTypeSqftBalconyTitle issued
11 · A-1011 bed1,167288Not yet
11 · A-1022 bed1,242186Not yet
11 · A-1032 bed1,230174Not yet
11 · A-1042 bed1,240189Not yet
11 · A-1052 bed1,697261Not yet
21 · A-2011 bed1,250360Not yet
21 · A-2022 bed1,234173Not yet
21 · A-2032 bed1,245189Not yet
21 · A-2042 bed1,236173Not yet
21 · A-2052 bed1,704229Not yet

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Al Wasl projects are tracking1 of the 3 nearest-to-finished are past their registered dates

ProjectBuilt%Registered date
Mr.c Residences Downtown50%Jan 2027
One Canal44%May 2025 · past date
DAMAC Citythis project38%Dec 2025 · past date
Casa Canal12%—

“Past date”: the registered date has already passed · 3 of 7 live Al Wasl projects past theirs · DLD register and inspections, October 2026

All 13 Al Wasl projects →

As registered with the Land DepartmentWhere DAMAC City is, and who is on its register row

Escrow agent
بنك الإمارات دبي الوطني (ش.م.ع)
Master developer
Meraas
Registered start
June 2022
Configuration
Tower(A):G+ 4P + 57 Tower(B):G+ 4P + 40 Residential, The project designed to have a concrete structure and block with internal and external finishes.
Pinned by Google from the registered name; verify the plot before relying on it.Open in Google Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in DAMAC City

Towers inside this project that have enough registered resales for their own record.

Ask about DAMAC City

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will DAMAC City be completed?
The developer registered handover for December 2025; that date has passed with no completion recorded, 7 months on, and the project was 38% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
What does DAMAC City cost per square foot?
AED 2,232 per sqft, the median of 51 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 2.90M. That is 30.7% below the Al Wasl off-plan median across 9 projects.
Is DAMAC City in escrow?
Yes: the Land Department register names بنك الإمارات دبي الوطني (ش.م.ع) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of DAMAC City?
The register names the master developer, Meraas, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
How many units does DAMAC City have?
509 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send DAMAC City to a client as a branded report

Create client report

Off-plan record for DAMAC City

Record type
Project-level off-plan register record
Data date
Evidence base
509 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/al-wasl/damac-city
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “DAMAC City, off-plan.” Al Wasl, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/al-wasl/damac-city