City Center Residences
Registered for handover in Q3 2026 and 72% built in September 2026. Off-plan units sell at AED 2.37M (AED 2,685/sqft), 30% below the Downtown Dubai off-plan median.
Off-plan price, typical unit
2.37MAED
AED 2,685/sqft · 30% below Downtown Dubai off-plan · 32 sales in 12 months
Started May 2022Registered handover Sept 2026
DLD inspection, 3 Sept 2026
- Median off-plan sale
- AED 2.37M
- Titles issued
- 0 of 383
- Escrow
- بنك الإمارات دبي الوطني (ش.م.ع)
Saves the tower’s record to your account.
Is City Center Residences a safe off-plan buy?In escrow; 72% built in its registered handover month
- Is it on schedule?72% built in September 2026 against a September 2026 handover: 28% left to build within the month · DLD inspection, 3 Sept 202672%Context
- Is my money protected?Payments go to an escrow account at بنك الإمارات دبي الوطني (ش.م.ع), as registered with the Land DepartmentEscrowContext
- Is the price fair?AED 2,685/sqft, 29.7% below the Downtown Dubai off-plan median across 17 projects-29.7%Context
- Is it selling?32 off-plan sales registered in the last 12 months, of 383 units; the latest on 24 Sept 202632Context
- Who is building it?Dar Global, licence no. 1221Context
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built383 units, mostly one-beds; none titled yet
DLD unit register · balconies a median 15% of unit area · median off-plan sale AED 2.37M
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
383 units in DLD’s register for City Center Residences, floor by floor.
Show 383 of 383 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Downtown Dubai projects are tracking1 of the 3 nearest-to-finished are past their registered dates
“Past date”: the registered date has already passed · 2 of 12 live Downtown Dubai projects past theirs · DLD register and inspections, October 2026
All 54 Downtown Dubai projects →As registered with the Land DepartmentWhere City Center Residences is, and who is on its register row
- Escrow agent
- بنك الإمارات دبي الوطني (ش.م.ع)
- Developer, as licensed
- DAR GLOBAL PROPERTIES L.L.C (no. 1221)
- Master developer
- Emaar Development
- Registered start
- May 2022
- Configuration
- Tower consists of 1B+G+4P+49F+1MECH+R+4UR Floors (Residential Commercial) with external and internal finishes.
Construction progress is DLD’s inspection of 3 Sept 2026. DLD’s published project register still lags it, so the later inspection is used and dated on its own. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in City Center Residences
Towers inside this project that have enough registered resales for their own record.
Ask about City Center Residences
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will City Center Residences be completed?
- The developer registered handover for September 2026, 0 months after DLD’s latest record, and the project was 72% built as of September 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department inspection of 3 Sept 2026.
- What does City Center Residences cost per square foot?
- AED 2,685 per sqft, the median of 32 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 2.37M. That is 29.7% below the Downtown Dubai off-plan median across 17 projects.
- Is City Center Residences in escrow?
- Yes: the Land Department register names بنك الإمارات دبي الوطني (ش.م.ع) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of City Center Residences?
- DAR GLOBAL PROPERTIES L.L.C, licence no. 1221, by the register’s own licence number; the master developer that owns the land is Emaar Development. Dubai Land Department project register as of July 2026.
- How many units does City Center Residences have?
- 383 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send City Center Residences to a client as a branded report
Off-plan record for City Center Residences
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 383 registered units; DLD project register as of 2026-07-06; construction state from the DLD inspection, 3 Sept 2026
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record
- /off-plan/apartments/dubai/downtown-dubai/city-center-residences
Cite as: Dubai Wealth Index. “City Center Residences, off-plan.” Downtown Dubai, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/downtown-dubai/city-center-residences