Registered for handover in Q3 2026 and 60% built in November 2026, 2 months past that date.
- Built
- 60%
- Registered handover Sept 2026 · overdue
- Typical unit, off-plan
- AED 1.17M
- AED 1,258/sqft · 27 sales in 12 months
- Against Dubai South
- −24%
- Off-plan median per sqft, 83 projects
- Registered units
- 35
- 0 with a title issued
Off-plan price, typical unit
1.17M AED
AED 1,258/sqft · 24% below Dubai South off-plan · 27 sales in 12 months
Started Apr 2025Registered handover Sept 2026 · overdue
DLD project register, Nov 2026
Project alerts are being built for Pro.
Register interest in alerts on Cresswell Plaza’s progress and handover date.
- Median off-plan sale
- AED 1.17M
- Titles issued
- 0 of 35
- Escrow
- بنك المشرق (شركة مساهمة عامة)
Saves the tower’s record to your account.
Escrow, progress and price In escrow; 60% built and 2 months past its registered handover
- Is it on schedule?60% built in November 2026, 2 months past its registered September 2026 handover · DLD project register, Nov 202660%Context
- Is my money protected?Payments go to an escrow account at بنك المشرق (شركة مساهمة عامة), as registered with the Land DepartmentEscrowContext
- Is the price fair?AED 1,258/sqft, 24.2% below the Dubai South off-plan median across 83 projects−24.2%Context
- Is it selling?27 off-plan sales registered in the last 12 months, of 35 units; the latest on 2 Nov 202627Context
- Who is building it?Essa Bokhowa, licence no. 2475Context
A registered date is not a delivery forecast · 67% of recorded completions carry their planned date to the day · DLD register, November 2026
What is being built35 units, mostly two-beds; none titled yet
DLD unit register · balconies a median 11% of unit area · median off-plan sale AED 1.17M
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a pending project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
35 units in DLD’s register for Cresswell Plaza, floor by floor.
Show 35 of 35 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Dubai South projects are trackingThe nearest-to-finished are all past their registered dates
“Past date”: the registered date has already passed · 15 of 76 pending Dubai South projects past theirs · DLD register and inspections, November 2026
All 100 Dubai South projects →As registered with the Land DepartmentWhere Cresswell Plaza is, and who is on its register row
- Escrow agent
- بنك المشرق (شركة مساهمة عامة)
- Developer, as licensed
- ESSA BOKHOWA PROPERTIES L.L.C (no. 2475)
- Master developer
- Dubai Aviation City Corporation
- Registered start
- April 2025
- Configuration
- G+4
Construction progress is the percentage DLD recorded in its project register as of November 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in Cresswell Plaza
Towers inside this project that have enough registered resales for their own record.
Ask an agent about Cresswell Plaza
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When is Cresswell Plaza handed over?
- The developer registered handover for September 2026; that date has passed with no completion recorded, 2 months on, and the project was 60% built as of November 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of November 2026.
- How far along is construction of Cresswell Plaza?
- Cresswell Plaza was 60% built as of November 2026, the Land Department’s recorded progress, not a developer claim. Dubai Land Department project register as of November 2026.
- Who is the developer of Cresswell Plaza?
- ESSA BOKHOWA PROPERTIES L.L.C, licence no. 2475, by the register’s own licence number; the master developer that owns the land is Dubai Aviation City Corporation. Dubai Land Department project register as of November 2026.
- What does Cresswell Plaza cost per square foot?
- AED 1,258 per sqft, the median of 27 registered off-plan sales in the 12 months to 2 Nov 2026; the median unit sold for AED 1.17M. That is 24.2% below the Dubai South off-plan median across 83 projects.
- Is Cresswell Plaza in escrow?
- Yes: the Land Department register names بنك المشرق (شركة مساهمة عامة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of November 2026.
- How many units does Cresswell Plaza have?
- 35 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of November 2026.
Send Cresswell Plaza to a client as a branded report
Create client reportOff-plan record for Cresswell Plaza
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 35 registered units; DLD project register as of 2026-11-01
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record
- /off-plan/apartments/dubai/dubai-south/cresswell-plaza
Cite as: Dubai Wealth Index. “Cresswell Plaza, off-plan.” Dubai South, Dubai. Register to 2026-11-01, data to 2026-11-02. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-south/cresswell-plaza