Saba 4

Under construction · 535 units · started Feb 2024 · Jumeirah Lake Towers

Registered for handover in Q2 2027 and 12% built in July 2026. Off-plan units sell at AED 3.36M (AED 2,550/sqft), 13% below the Jumeirah Lake Towers off-plan median.

Off-plan price, typical unit

3.36MAED

AED 2,550/sqft · 13% below Jumeirah Lake Towers off-plan · 52 sales in 12 months

Built12%

Started Feb 2024Registered handover Jun 2027

DLD project register, Jul 2026

Median off-plan sale
AED 3.36M
Titles issued
0 of 535
Escrow
بنك الإمارات دبي الوطني (ش.م.ع)

Saves the tower’s record to your account.

Is Saba 4 a safe off-plan buy?In escrow; 12% built with 11 months to its registered handover; no record of the builder

  1. Is it on schedule?12% built in July 2026 against a June 2027 handover: 88% left to build in 11 months · DLD project register, Jul 202612%Context
  2. Is my money protected?Payments go to an escrow account at بنك الإمارات دبي الوطني (ش.م.ع), as registered with the Land DepartmentEscrowContext
  3. Is the price fair?AED 2,550/sqft, 13.3% below the Jumeirah Lake Towers off-plan median across 19 projects-13.3%Context
  4. Is it selling?52 off-plan sales registered in the last 12 months, of 535 units; the latest on 20 Jul 202652Context
  5. Who is building it?The register names the master developer, DMCC; the builder is not recordedNo record

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

Check an asking price →How each reading works →

What is being built535 units, mostly one-beds and two-beds; none titled yet

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
Studio1768–7680
1 bed267888–1,0270
2 bed1781,404–1,4990
3 bed892,193–2,1990

DLD unit register · balconies a median 19% of unit area · median off-plan sale AED 3.36M

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

535 units in DLD’s register for Saba 4, floor by floor.

Show 400 of 535 units
FloorUnitTypeSqftBalconyTitle issued
51 · 5012 bed1,420275Not yet
51 · 5023 bed2,227597Not yet
51 · 5031 bed966170Not yet
51 · 5042 bed1,529510Not yet
51 · 5051 bed915201Not yet
51 · 5061 bed1,049202Not yet
51 · 507Studio768144Not yet
61 · 6012 bed1,412261Not yet
61 · 6023 bed2,193561Not yet
61 · 6031 bed971167Not yet

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Jumeirah Lake Towers projects are trackingThe nearest-to-finished are all past their registered dates

ProjectBuilt%Registered date
Me Do Re 295%Dec 2025 · past date
The Wind Tower II85%Jun 2023 · past date
The Wind Tower I75%Jun 2023 · past date
Saba 4this project12%Jun 2027

“Past date”: the registered date has already passed · 8 of 15 live Jumeirah Lake Towers projects past theirs · DLD register and inspections, October 2026

All 48 Jumeirah Lake Towers projects →

As registered with the Land DepartmentWhere Saba 4 is, and who is on its register row

Escrow agent
بنك الإمارات دبي الوطني (ش.م.ع)
Master developer
DMCC
Registered start
February 2024
Configuration
3 B + G + 4P + 45 F + 1 MECH+ Roof.The project designed to have a concrete structure and block with internal and external finishes.
Pinned by Google from the registered name; verify the plot before relying on it.Open in Google Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in Saba 4

Towers inside this project that have enough registered resales for their own record.

Ask about Saba 4

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will Saba 4 be completed?
The developer registered handover for June 2027, 11 months after DLD’s latest record, and the project was 12% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
What does Saba 4 cost per square foot?
AED 2,550 per sqft, the median of 52 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 3.36M. That is 13.3% below the Jumeirah Lake Towers off-plan median across 19 projects.
Is Saba 4 in escrow?
Yes: the Land Department register names بنك الإمارات دبي الوطني (ش.م.ع) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of Saba 4?
The register names the master developer, DMCC, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
How many units does Saba 4 have?
535 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send Saba 4 to a client as a branded report

Create client report

Off-plan record for Saba 4

Record type
Project-level off-plan register record
Data date
Evidence base
535 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/jumeirah-lake-towers/saba-4
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Saba 4, off-plan.” Jumeirah Lake Towers, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/jumeirah-lake-towers/saba-4