The Melgrano
Registered for handover in Q4 2026 and 43% built in October 2026.
Started Nov 2024Registered handover Dec 2026
DLD inspection, 8 Oct 2026
- Titles issued
- 0 of 13
- Escrow
- بنك ابوظبى التجارى
Is The Melgrano a safe off-plan buy?In escrow; 43% built with 2 months to its registered handover; no record of off-plan sales
- Is it on schedule?43% built in October 2026 against a December 2026 handover: 57% left to build in 2 months · DLD inspection, 8 Oct 202643%Context
- Is my money protected?Payments go to an escrow account at بنك ابوظبى التجارى, as registered with the Land DepartmentEscrowContext
- Is the price fair?Off-plan prices are read across a project’s published towers, and this one has none yetNo record
- Is it selling?Off-plan sales are counted across a project’s published towers, and this one has none yetNo record
- Who is building it?The Melgrano, licence no. 1582Context
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built13 units, mostly four-plus-beds; none titled yet
DLD unit register · balconies a median 29% of unit area
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
13 units in DLD’s register for The Melgrano, floor by floor.
Show 13 of 13 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Jumeirah projects are tracking1 of the 3 nearest-to-finished are past their registered dates
“Past date”: the registered date has already passed · 1 of 6 live Jumeirah projects past theirs · DLD register and inspections, October 2026
All 9 Jumeirah projects →As registered with the Land DepartmentWhere The Melgrano is, and who is on its register row
- Escrow agent
- بنك ابوظبى التجارى
- Developer, as licensed
- THE MELGRANO REAL ESTATE DEVELOPMENT L.L.C (no. 1582)
- Master developer
- Meraas
- Registered start
- November 2024
- Configuration
- 1B+ G +1M +7 +1R.The project designed to have a concrete structure and block with internal and external finishes.
Construction progress is DLD’s inspection of 8 Oct 2026. DLD’s published project register still lags it, so the later inspection is used and dated on its own. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Ask about The Melgrano
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will The Melgrano be completed?
- The developer registered handover for December 2026, 2 months after DLD’s latest record, and the project was 43% built as of October 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department inspection of 8 Oct 2026.
- Is The Melgrano in escrow?
- Yes: the Land Department register names بنك ابوظبى التجارى as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of The Melgrano?
- THE MELGRANO REAL ESTATE DEVELOPMENT L.L.C, licence no. 1582, by the register’s own licence number; the master developer that owns the land is Meraas. Dubai Land Department project register as of July 2026.
- How many units does The Melgrano have?
- 13 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send The Melgrano to a client as a branded report
Off-plan record for The Melgrano
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 13 registered units; DLD project register as of 2026-07-06; construction state from the DLD inspection, 8 Oct 2026
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record
- /off-plan/apartments/dubai/jumeirah/the-melgrano
Cite as: Dubai Wealth Index. “The Melgrano, off-plan.” Jumeirah, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/jumeirah/the-melgrano