Dubailand, delivery record

Edition DWI-DEVELOPER-DUBAILAND
Registered projects
23
DLD register, Jul 2026
Delivered on time
100%
of 6 completed
Median slippage
0months
registered date to recorded completion
Live and overdue
3
of 14 live

Every project the Dubai Land Department registers to دبي لاند (ش.ذ.م.م), which this site publishes as Dubailand — a high-confidence reading of the registered Arabic name. On-time delivery and slippage are measured on completed projects against the completion date the developer itself registered. A live project past that date is counted as overdue, not as late: it has not been delivered yet, and this site does not forecast when it will be. 3 projects are recorded as cancelled.

Live projects

14 registered and not yet recorded complete, most advanced first.

ProjectLocalityRegistered handoverPast plan, monthsBuilt, %Units, registered
PalmarosaAl WahaOct 202245 mo97282
Living Legends Phase 7Living LegendsSept 202158 mo92343
California VillageCity of ArabiaJul 202512 mo79212
Haven By Aldar 3Haven by AldarMar 2028in 20 mo3292
Haven By Aldar 1Haven by AldarNov 2027in 16 mo2462
Haven By Aldar 2Haven by Aldar2474
Verdes by Haven 2Dubailand Residence ComplexJun 2028in 23 mo259
Verdes by Haven 1Dubailand Residence ComplexMay 2028in 22 mo1988
Rise by Athlon 2Dubailand Residence ComplexJan 2030in 42 mo0407
Rise by Athlon 3Dubailand Residence ComplexJan 2030in 42 mo0120
Rise by Athlon 4Dubailand Residence ComplexDec 2029in 41 mo066
Rise by Athlon 1Dubailand Residence ComplexDec 2029in 41 mo0650
California ResidencesCity of ArabiaApr 2028in 21 mo0369
Mirdif Hills - Asayel AvenueMirdifMay 2027in 10 mo0193

Delivered projects

6 recorded complete, most recent first. Slippage is months from the registered date to the recorded one; negative is early.

ProjectLocalityRegisteredCompletedSlippage, months
RukanAl WahaJan 2023Jan 2023on time
Rukan2RukanAug 2022Aug 2022on time
DAMAC Hills - ArtesiaDamac HillsJan 2021Jan 2021on time
Seventh HeavenAl BarariSept 2020Sept 2020on time
DAMAC Hills - LoretoDamac HillsDec 2017Dec 2017on time
The Sustainable CityThe Sustainable CityApr 2017Dec 2015-16

Dubailand, delivery record

Record type
Developer-level off-plan register record
Data date
Evidence base
23 registered projects, 6 completed; DLD project register as of 2026-07-06; identity high-confidence
Sources
Dubai Land Department project register
Canonical record
/developers/dubailand
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Dubailand, delivery record.” Register to 2026-07-06, data to 2026-08-26. https://dubaiwealthindex.com/developers/dubailand.