Off-plan · DLD project register as of 6 Jul 2026

Aykon City 3

Under construction · 1,287 units · started Dec 2019 · Business Bay

Registered for handover in Q4 2027 and 23% built in July 2026. Off-plan units sell at AED 2.58M (AED 2,499/sqft), 7% below the Business Bay off-plan median.

Off-plan price, typical unit

2.58MAED

AED 2,499/sqft · 7% below Business Bay off-plan · 55 sales in 12 months

Built23%

Started Dec 2019Registered handover Dec 2027

DLD project register, Jul 2026

Median off-plan sale
AED 2.58M
Titles issued
0 of 1,287
Escrow
بنك الإمارات دبي الوطني (ش.م.ع)

Is Aykon City 3 a safe off-plan buy?In escrow; 23% built with 17 months to its registered handover; no record of the builder

  1. Is it on schedule?23% built in July 2026 against a December 2027 handover: 77% left to build in 17 months · DLD project register, Jul 202623%Context
  2. Is my money protected?Payments go to an escrow account at بنك الإمارات دبي الوطني (ش.م.ع), as registered with the Land DepartmentEscrowContext
  3. Is the price fair?AED 2,499/sqft, 6.9% below the Business Bay off-plan median across 47 projects-6.9%Context
  4. Is it selling?55 off-plan sales registered in the last 12 months, of 1,287 units; the latest on 12 Oct 202655Context
  5. Who is building it?The register names the master developer, Meraas; the builder is not recordedNo record

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

How each reading works →

What is being built1,287 units, mostly one-beds and two-beds; none titled yet

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
Studio107357–6990
1 bed607743–8550
2 bed4481,100–1,4300
3 bed1221,485–1,9200
4+ bed35,042–13,4320

DLD unit register · balconies a median 14% of unit area · median off-plan sale AED 2.58M

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

1,287 units in DLD’s register for Aykon City 3, floor by floor.

Show 400 of 1,287 units
FloorUnitTypeSqftBalconyTitle issued
91 · A9011 bed749105Not yet
91 · A9021 bed75197Not yet
91 · A9031 bed75396Not yet
91 · A9041 bed74496Not yet
91 · A9051 bed787105Not yet
94 · D9011 bed76389Not yet
94 · D9021 bed769104Not yet
94 · D9031 bed770106Not yet
94 · D9041 bed772104Not yet
94 · D9051 bed786103Not yet

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Business Bay projects are tracking2 of the 3 nearest-to-finished are past their registered dates

ProjectBuilt%Registered date
Burj Pacific99%Jan 2023 · past date
Al Habtoor Tower90%Dec 2026
West Bay Tower77%Feb 2024 · past date
Aykon City 3this project23%Dec 2027

“Past date”: the registered date has already passed · 12 of 30 live Business Bay projects past theirs · DLD register and inspections, October 2026

All 117 Business Bay projects →

As registered with the Land DepartmentWhere Aykon City 3 is, and who is on its register row

Escrow agent
بنك الإمارات دبي الوطني (ش.م.ع)
Master developer
Meraas
Registered start
December 2019
Configuration
Project consists of one residential Building (Tower A+D) configuration of 1B+G+10P+73F+3Mec+R. It is designed to have a concrete structure and block with internal & external finishes.
Pills show median resale price per sqft, AED. 2 of 2 published towers pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in Aykon City 3

Towers inside this project that have enough registered resales for their own record.

Ask about Aykon City 3

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will Aykon City 3 be completed?
The developer registered handover for December 2027, 17 months after DLD’s latest record, and the project was 23% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
What does Aykon City 3 cost per square foot?
AED 2,499 per sqft, the median of 55 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 2.58M. That is 6.9% below the Business Bay off-plan median across 47 projects.
Is Aykon City 3 in escrow?
Yes: the Land Department register names بنك الإمارات دبي الوطني (ش.م.ع) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of Aykon City 3?
The register names the master developer, Meraas, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
How many units does Aykon City 3 have?
1,287 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send Aykon City 3 to a client as a branded report

Create client report

Off-plan record for Aykon City 3

Record type
Project-level off-plan register record
Data date
Evidence base
1,287 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/business-bay/aykon-city-3
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Aykon City 3, off-plan.” Business Bay, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/business-bay/aykon-city-3