Off-plan · DLD project register as of 6 Jul 2026

The Atria

Completed 2018 · 218 units · started Feb 2014 · Business Bay

Recorded complete in April 2018.

Built100%

Started Feb 2014Completed Apr 2018

DLD project register, Jul 2026

Titles issued
218 of 218
Escrow
بنك دبي الاسلامي (شركة مساهمة عامة)

Is The Atria a safe off-plan buy?Recorded complete in April 2018

  1. Is it on schedule?Recorded complete in April 2018, on its registered date to the day: the register often stamps one onto the other · DLD project register, Jul 2026100%Context
  2. Is my money protected?The register named the escrow agent: بنك دبي الاسلامي (شركة مساهمة عامة)EscrowContext
  3. Is the price fair?No off-plan sale registered in 12 months to price it onNo record
  4. Is it selling?No off-plan sale registered in 12 months; the last in December 20180Context
  5. Who is building it?Deyaar Development, licence no. 15; 0 of its 7 dated live projects are past their registered dates0%Context

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

How each reading works →

What is being built218 units, mostly two-beds and one-beds; all titled

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
Studio1689–6891
1 bed81867–1,09481
2 bed1021,447–1,572102
3 bed332,178–2,75733
4+ bed19,620–9,6201

DLD unit register · balconies a median 9% of unit area

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

218 units in DLD’s register for The Atria, floor by floor.

Show 218 of 218 units
FloorUnitTypeSqftBalconyTitle issued
11 · 1011 bed760—Yes
11 · 1021 bed803—Yes
21 · 2012 bed1,52259Yes
21 · 2032 bed1,447118Yes
21 · 2051 bed89459Yes
21 · 2061 bed87659Yes
21 · 2071 bed86859Yes
21 · 2081 bed1,059225Yes
21 · 2092 bed1,500159Yes
21 · 2103 bed2,451176Yes

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Business Bay projects are tracking2 of the 3 nearest-to-finished are past their registered dates

ProjectBuilt%Registered date
Burj Pacific99%Jan 2023 · past date
Al Habtoor Tower90%Dec 2026
West Bay Tower77%Feb 2024 · past date

“Past date”: the registered date has already passed · 12 of 30 live Business Bay projects past theirs · DLD register and inspections, October 2026

All 117 Business Bay projects →

As registered with the Land DepartmentWhere The Atria is, and who is on its register row

Escrow agent
بنك دبي الاسلامي (شركة مساهمة عامة)
Developer, as licensed
DEYAAR DEVELOPMENT (P.J.S.C) (no. 15)
Master developer
Business Bay LLC
Registered start
February 2014
Configuration
PROPOSED TWO TOWERS. FIRST ONE (3B+G+31TYP), SECOND ONE (3B+G+30TYP)
Pills show median resale price per sqft, AED. 2 of 2 published towers pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in The Atria

Towers inside this project that have enough registered resales for their own record.

More from Deyaar Development

Live projects registered to the same developer, most advanced first.

Ask about The Atria

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will The Atria be completed?
The register records The Atria complete in April 2018. Dubai Land Department project register as of July 2026.
Is The Atria in escrow?
Yes: the Land Department register names بنك دبي الاسلامي (شركة مساهمة عامة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of The Atria?
DEYAAR DEVELOPMENT (P.J.S.C), licence no. 15, by the register’s own licence number; the master developer that owns the land is Business Bay LLC. Dubai Land Department project register as of July 2026.
How many units does The Atria have?
218 registered units, of which 218 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send The Atria to a client as a branded report

Create client report

Off-plan record for The Atria

Record type
Project-level off-plan register record
Data date
Evidence base
218 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/business-bay/the-atria
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “The Atria, off-plan.” Business Bay, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/business-bay/the-atria