Creek Horizon

Completed 2020 · 556 units · started Dec 2016 · Dubai Creek Harbour

Recorded complete in September 2020.

Built100%

Started Dec 2016Completed Sept 2020

DLD project register, Jul 2026

Titles issued
556 of 556
Escrow
بنك دبي التجاري (ش.م.ع)

Is Creek Horizon a safe off-plan buy?Recorded complete in September 2020

  1. Is it on schedule?Recorded complete in September 2020, on its registered date to the day: the register often stamps one onto the other · DLD project register, Jul 2026100%Context
  2. Is my money protected?The register named the escrow agent: بنك دبي التجاري (ش.م.ع)EscrowContext
  3. Is the price fair?No off-plan sale registered in 12 months to price it onNo record
  4. Is it selling?No off-plan sale registered in 12 months; the last in April 20220Context
  5. Who is building it?The Lagoons Phase One, licence no. 1038Context

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

How each reading works →

What is being built556 units, mostly one-beds and two-beds; all titled

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
1 bed207751–771207
2 bed2001,127–1,214200
3 bed1351,625–1,685135
4+ bed142,947–3,27414

DLD unit register · balconies a median 10% of unit area

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

556 units in DLD’s register for Creek Horizon, floor by floor.

Show 400 of 556 units
FloorUnitTypeSqftBalconyTitle issued
11 · 1032 bed1,12875Yes
11 · 1041 bed77175Yes
11 · 1051 bed76875Yes
11 · 1061 bed75461Yes
12 · 1012 bed1,211128Yes
12 · 1051 bed76773Yes
12 · 1061 bed75160Yes
12 · 1073 bed1,621166Yes
12 · 1082 bed1,183128Yes
13 · TH014+ bed3,363906Yes

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Dubai Creek Harbour projects are trackingThe nearest-to-finished are all within their registered dates

ProjectBuilt%Registered date
Creek Waters50%Sept 2027
Creek Waters 247%Dec 2027
Aeon20%—

“Past date”: the registered date has already passed · 0 of 10 live Dubai Creek Harbour projects past theirs · DLD register and inspections, October 2026

All 45 Dubai Creek Harbour projects →

As registered with the Land DepartmentWhere Creek Horizon is, and who is on its register row

Escrow agent
بنك دبي التجاري (ش.م.ع)
Developer, as licensed
THE LAGOONS PHASE ONE L.L.C (no. 1038)
Master developer
The Lagoons Phase 1
Registered start
December 2016
Configuration
Podium & Townhouse: 2B+G+3P+2F+R Tower 1: 2B+G+3P+39F+R Tower 2: 2B+G+3P+36F+R
Pills show median resale price per sqft, AED. 2 of 2 published towers pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in Creek Horizon

Towers inside this project that have enough registered resales for their own record.

More from The Lagoons Phase One

Live projects registered to the same developer, most advanced first.

Ask about Creek Horizon

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will Creek Horizon be completed?
The register records Creek Horizon complete in September 2020. Dubai Land Department project register as of July 2026.
Is Creek Horizon in escrow?
Yes: the Land Department register names بنك دبي التجاري (ش.م.ع) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of Creek Horizon?
THE LAGOONS PHASE ONE L.L.C, licence no. 1038, by the register’s own licence number; the master developer that owns the land is The Lagoons Phase 1. Dubai Land Department project register as of July 2026.
How many units does Creek Horizon have?
556 registered units, of which 556 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send Creek Horizon to a client as a branded report

Create client report

Off-plan record for Creek Horizon

Record type
Project-level off-plan register record
Data date
Evidence base
556 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/dubai-creek-harbour/creek-horizon
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Creek Horizon, off-plan.” Dubai Creek Harbour, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-creek-harbour/creek-horizon