Delivery record · DLD project register as of 06 Jul 2026

Emaar Properties

113 registered projects · 88 completed · 25 live · 12th of 22 developers on delivery

2 of Emaar’s 23 dated live projects are past the completion date it registered itself: 9%, against 13% across the 28 Dubai developers with ten or more registered projects. Its most-traded tower, Burj Khalifa, registered 115 sales in the last 12 months at a median AED 5.00M (AED 2,929/sqft).

Live projects past their registered date

9%2 of 23

28 developers with ten or more projects: 13%

Object One 0%Emaar 9%Dubai 13%
Registered projects
113
Completed
88
Live, no registered date
2

Does Emaar deliver on time?Fewer of its live projects are past their own dates than Dubai’s share; its most-traded tower sells at a typical AED 5.00M (AED 2,929/sqft)

  1. Are live projects on time?2 of 23 dated live projects are past the date Emaar registered; 2 more carry no date9%Context
  2. How does it rank?12th of the 22 developers ranked on delivery, fewest overdue first; Dubai’s share past date is 13%12thContext
  3. How late, typically?Median 3 months early over 21 completions with a date distinct from the plan; 65 more were stamped with it−3 moContext
  4. Do its towers trade?Burj Khalifa trades at AED 2,929/sqft on 115 sales, off-plan and ready, in 12 months; 60 or more of its towers have a sale recordAED 5.00MContext

Ranked on the share of live projects past their own registered date · fewest first · register Jul 2026

All 28 developers →

Live projects, most advanced firstEmirates Hills is 100% built and 311 months past its date

ProjectBuiltRegisteredPast dateUnits
Emirates HillsEmirates Hills100%Aug 2000311 mo26
Arabian Ranches lll - Bliss 2Arabian Ranches 388%Dec 20257 mo269
Marina ShoresDubai Marina87%Dec 2026in 7 mo440
The St. Regis Residences, Downtown DubaiDowntown Dubai76%Dec 2026in 7 mo1,097
Address The BayDubai Harbour70%Dec 2026in 5 mo447
The Valley - RivanaThe Valley64%Mar 2027in 8 mo486
The Valley - AlanaThe Valley48%no date—322
The Valley - NimaThe Valley36%no date—520
BayviewDubai Harbour18%Jul 2028in 24 mo676
The Valley - VeneraThe Valley11%Sept 2028in 26 mo696
SeapointDubai Harbour10%Mar 2028in 20 mo661
The Valley - VeloraThe Valley8%Aug 2028in 25 mo488
The Valley - Avena 2The Valley7%Jul 2028in 24 mo332
The Valley - Velora 2The Valley6%Jul 2028in 24 mo312
The Valley - ElvaThe Valley5%Oct 2028in 27 mo244
The Valley - EleaThe Valley3%Jun 2028in 23 mo128
The Valley - AvenaThe Valley2%Jun 2028in 23 mo322
The Valley - Farm Grove 2The Valley1%Oct 2028in 27 mo290
The Valley - Farm GroveThe Valley1%Dec 2028in 29 mo482
Terra HeightsExpo City1%Mar 2029in 32 mo1,004
The Valley - KaiaThe Valley0%Jul 2028in 24 mo156
THE BRISTOL Emaar BeachfrontDubai Harbour0%Sept 2029in 38 mo227
Marina CoveDubai Marina0%Sept 2029in 38 mo226
The Valley - VinderaThe Valley0%Dec 2028in 29 mo745
The Valley - RiveraThe Valley0%Nov 2028in 28 mo378

Built % and dates from the DLD register, Jul 2026 · months past date at that register date · a live project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be

Delivered projects, most recent first88 completed; the median measurable completion came 3 months early

Show the 88 delivered projects
ProjectRegisteredCompletedSlippage, months
Arabian Ranches lll - Anya 2Arabian Ranches 3Dec 2026Oct 2026-2
Arabian Ranches lll - AnyaArabian Ranches 3Oct 2026Oct 2026on time
Beachgate by AddressDubai HarbourDec 2026Sept 2026-3
THE RESIDENCE | Burj KhalifaDowntown DubaiDec 2024Sept 2026+21
Arabian Ranches lll - MayArabian Ranches 3Sept 2027Aug 2026-13
The Valley - LilliaThe Valley—Jul 2026—
Golf HeightsThe GreensDec 2026Jun 2026-6
The Valley - EloraThe ValleySept 2026Mar 2026-6
The Valley - OraniaThe ValleyDec 2025Dec 2025stamped
Arabian Ranches lll - RayaArabian Ranches 3Jun 2026Dec 2025-6
Beach MansionDubai HarbourDec 2025Nov 2025-1
Palace Beach ResidenceDubai HarbourOct 2025Oct 2025stamped
Arabian Ranches lll - JuneArabian Ranches 3Jun 2025Jun 2025stamped
The Valley - TaliaThe ValleyMar 2025Mar 2025stamped
The Valley-NaraThe ValleyDec 2024Dec 2024stamped
Arabain Ranches lll - BlissArabian Ranches 3Nov 2024Nov 2024stamped
Arabian Ranches lll - June 2Arabian Ranches 3Oct 2024Oct 2024stamped
Burj CrownDowntown DubaiAug 2023Aug 2023stamped
The Valley - EdenThe ValleyJun 2023Jun 2023stamped
Grand Bleu Tower interiors by Elie SaabDubai HarbourMay 2023May 2023stamped
Beach IsleDubai HarbourApr 2023Apr 2023stamped
The Address Dubai OperaDowntown DubaiMar 2023Mar 2023stamped
Marina VistaDubai HarbourMar 2023Mar 2023stamped
Arabian Ranches lll - RubaArabian Ranches 3Mar 2023Mar 2023stamped
Arabian Ranches III - SUNArabian Ranches 3Dec 2022Dec 2022stamped
Il PRIMODowntown DubaiDec 2022Dec 2022stamped
ForteDowntown DubaiNov 2022Nov 2022stamped
Arabian Ranches III - SpringArabian Ranches 3Oct 2022Oct 2022stamped
Downtown Views IIZabeelAug 2022Aug 2022stamped
Arabian Ranches III - JOYArabian Ranches 3Aug 2022Aug 2022stamped
GrandeDowntown DubaiJun 2022Jun 2022stamped
Vida Dubai MallDowntown DubaiDec 2022Feb 2022-10
VIDA Residences Dubai MarinaDubai MarinaNov 2022Feb 2022-9
Act One | Act TwoDowntown DubaiDec 2022Jan 2022-11
AR II CameliaArabian Ranches 2Jan 2022Jan 2022stamped
Beach VistaDubai HarbourJan 2022Jan 2022stamped
Opera GrandDowntown DubaiDec 2021Dec 2021stamped
AR II Camelia 2Arabian Ranches 2Nov 2021Nov 2021stamped
Sunrise BayDubai HarbourOct 2021Oct 2021stamped
Downtown ViewsZabeelJun 2021Jun 2021stamped
5242Dubai MarinaSept 2020Sept 2020stamped
Blvd HeightsDowntown DubaiApr 2020Apr 2020stamped
Boulevard PointDowntown DubaiFeb 2020Dec 2019-2
AR II - Reem CommunityArabian Ranches 2Jan 2020Dec 2019-1
The Address Residence - Sky ViewDowntown DubaiSept 2019Sept 2019stamped
The Address Residence Fountain Views IIDowntown DubaiJul 2019Jul 2019stamped
Arabian Ranches- Azalea CommunityArabian Ranches 2May 2019May 2019stamped
The HillsThe GreensApr 2019Apr 2019stamped
AseelArabian RanchesOct 2018Oct 2018stamped
Blvd CrescentDowntown DubaiMay 2019Jul 2018-10
Vida Residence Downtown DubaiDowntown DubaiMar 2019May 2018-10
Burj VistaDowntown DubaiApr 2017Apr 2017stamped
The Address Residence Fountain Views IIIDowntown DubaiSept 2019Dec 2016-33
PanoramaThe GreensJan 2015Jan 2015stamped
Alma-2Arabian RanchesFeb 2013Feb 2014+12
29 BoulevardDowntown DubaiApr 2013Apr 2013stamped
DD Stand PointDowntown DubaiDec 2012Dec 2012stamped
DD Boulevard CentralDowntown DubaiAug 2012Aug 2012stamped
Claren 1Downtown DubaiNov 2011Jul 2012+8
Burj Khalifa TowersDowntown DubaiJan 2012Jan 2012stamped
MoselaThe GreensSept 2010Sept 2010stamped
TanaroThe GreensSept 2010Sept 2010stamped
Park IslandsDubai MarinaMar 2010Mar 2010stamped
Marina QuaysDubai MarinaJan 2010Jan 2010stamped
Dubai Marina MallDubai MarinaDec 2009Dec 2009stamped
The Lakes ZulalThe LakesJan 2006Nov 2009+46
Burj ViewsDowntown DubaiSept 2009Sept 2009stamped
The Dubai MallDowntown DubaiAug 2008Aug 2008stamped
Arabian Ranches - Alvorada IIIArabian RanchesMay 2008May 2008stamped
Emirates Living - Springs 11The SpringsOct 2004May 2008+43
The Lakes GhadeerThe LakesJan 2007Jan 2007stamped
Emirates Living - Springs 2The SpringsFeb 2005Feb 2005stamped
Emirates Living - Springs 1The SpringsFeb 2005Feb 2005stamped
Emirates Living - Springs 10The SpringsJan 2005Jan 2005stamped
Emirates Living - Springs 8The SpringsJan 2005Jan 2005stamped
Emirates Living - Springs 9The SpringsJan 2005Jan 2005stamped
Emirates Living - Springs 12The SpringsJan 2005Jan 2005stamped
Emirates Living - Springs 6The SpringsDec 2004Dec 2004stamped
Emirates Living - Springs 5The SpringsDec 2004Dec 2004stamped
Emirates Living - Springs 14The SpringsOct 2004Oct 2004stamped
Emirates Living - Springs 15The SpringsOct 2004Oct 2004stamped
Emirates Living - Springs 7The SpringsSept 2004Sept 2004stamped
Emirates Living - Springs 4The SpringsJan 2004Apr 2004+3
Emirates Living - Springs 3The SpringsJan 2004Jan 2004stamped
The Lakes Deema 4The LakesJan 2003Jan 2003stamped
The Lakes Deema 3The LakesJan 2003Jan 2003stamped
The Lakes - Deema 1The LakesJan 2003Jan 2003stamped
The Lakes Deema 2The LakesJan 2003Jan 2003stamped

Slippage is months from the registered date to the recorded one; negative is early. The register dates 65 of these 88 completions to the registered day exactly — it writes the completion date onto the planned one — so those are marked “stamped” and left out of the median rather than counted as on time.

Emaar towers on the marketIts towers trade between AED 1,703 and 5,147 per sqft

BuildingMedian price, last 12 monthsSalesFollow
Burj KhalifaDowntown DubaiAED 5.00MAED 2,929/sqft4.5% gross yield115
The St. Regis Residences - Tower 1Downtown DubaiAED 3.70MAED 3,328/sqft67
GrandeDowntown DubaiAED 5.45MAED 3,539/sqft3.5% gross yield61
The St. Regis Residences - Tower 2Downtown DubaiAED 3.91MAED 2,975/sqft56
Burj CrownDowntown DubaiAED 2.60MAED 2,761/sqft5.0% gross yield51
The Address - The BLVDDowntown DubaiAED 4.85MAED 3,771/sqft3.9% gross yield43
Golf HeightsThe GreensAED 3.50MAED 2,542/sqft2.4% gross yield41
Forte T1Downtown DubaiAED 3.20MAED 2,837/sqft5.5% gross yield40

Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 60+

Every project the Dubai Land Department registers to Emaar Properties, matched by the developer licence number on each registration across the 3 licensed companies this name covers — a high-confidence identity.

Common questions

Are Emaar's off-plan projects on time?
2 of Emaar's 23 dated live projects are past the completion date the developer registered itself (9%), against 13% across the 28 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-07-06.
How does Emaar rank against other Dubai developers on delivery?
Emaar ranks 12th of the 22 developers ranked on delivery, fewest live projects past their registered date first. Only developers with at least 5 live projects are ranked. Dubai Land Department project register to 2026-07-06.
How late are Emaar's completed projects, typically?
The median measurable completion finished 3 months before its registered date, over 21 completions; 71% of those landed on or before it. 65 more completions were dated to the registered day exactly, where no slippage is observable, and are excluded. Dubai Land Department project register to 2026-07-06.
How many projects has Emaar registered in Dubai?
113 registered projects: 25 live, 88 completed. Projects are matched to Emaar Properties by the developer licence number on each registration. Dubai Land Department project register to 2026-07-06.
What do Emaar's towers sell for?
Its most-traded tower, Burj Khalifa, sold at a median AED 2,929/sqft across 115 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.

For agents

Send Emaar’s delivery record to a client

Open plain-text record

Emaar Properties, delivery record

Record type
Developer-level off-plan register record
Data date
Evidence base
113 registered projects, 25 live of which 2 past their registered date, 21 completions with a measurable slippage of 88 completed; DLD project register as of 2026-07-06; identity high-confidence over 3 licensed companies
Sources
Dubai Land Department project register
Canonical record
/developers/emaar-properties
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Emaar Properties, delivery record.” Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/developers/emaar-properties