Off-plan · DLD project register as of 6 Jul 2026

Creek Waters 2

Under construction · 455 units · started Aug 2023 · Dubai Creek Harbour

Registered for handover in Q4 2027 and 47% built in July 2026. Off-plan units sell at AED 2.48M (AED 2,335/sqft), 11% below the Dubai Creek Harbour off-plan median.

Off-plan price, typical unit

2.48MAED

AED 2,335/sqft · 11% below Dubai Creek Harbour off-plan · 46 sales in 12 months

Built47%

Started Aug 2023Registered handover Dec 2027

DLD project register, Jul 2026

Median off-plan sale
AED 2.48M
Titles issued
0 of 455
Escrow
بنك أبوظبي الأول ش.م.ع.

Saves the tower’s record to your account.

Is Creek Waters 2 a safe off-plan buy?In escrow; 47% built with 17 months to its registered handover

  1. Is it on schedule?47% built in July 2026 against a December 2027 handover: 53% left to build in 17 months · DLD project register, Jul 202647%Context
  2. Is my money protected?Payments go to an escrow account at بنك أبوظبي الأول ش.م.ع., as registered with the Land DepartmentEscrowContext
  3. Is the price fair?AED 2,335/sqft, 10.7% below the Dubai Creek Harbour off-plan median across 19 projects-10.7%Context
  4. Is it selling?46 off-plan sales registered in the last 12 months, of 455 units; the latest on 8 Oct 202646Context
  5. Who is building it?The Lagoons Phase One, licence no. 1038Context

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

Check an asking price →How each reading works →

What is being built455 units, mostly one-beds and two-beds; none titled yet

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
1 bed185755–9180
2 bed1801,132–1,2450
3 bed671,599–2,9230
4+ bed232,435–2,7690

DLD unit register · balconies a median 10% of unit area · median off-plan sale AED 2.48M

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

455 units in DLD’s register for Creek Waters 2, floor by floor.

Show 400 of 455 units
FloorUnitTypeSqftBalconyTitle issued
11 · 1012 bed1,240179Not yet
11 · 1021 bed75777Not yet
11 · 1031 bed90075Not yet
11 · 1041 bed77783Not yet
11 · 1051 bed75583Not yet
11 · 1061 bed75583Not yet
11 · 1072 bed1,19378Not yet
B11 · B1012 bed1,239153Not yet
B11 · B1022 bed1,269177Not yet
B11 · B1032 bed1,274182Not yet

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Dubai Creek Harbour projects are trackingThe nearest-to-finished are all within their registered dates

ProjectBuilt%Registered date
Creek Waters50%Sept 2027
Creek Waters 2this project47%Dec 2027
Aeon20%—
Oria20%—

“Past date”: the registered date has already passed · 0 of 10 live Dubai Creek Harbour projects past theirs · DLD register and inspections, October 2026

All 45 Dubai Creek Harbour projects →

As registered with the Land DepartmentWhere Creek Waters 2 is, and who is on its register row

Escrow agent
بنك أبوظبي الأول ش.م.ع.
Developer, as licensed
THE LAGOONS PHASE ONE L.L.C (no. 1038)
Master developer
The Lagoons Phase 1
Registered start
August 2023
Configuration
2B+G+P+50 Residential+Retail,The project designed to have a concrete structure and block with internal and external finishes.
Pinned by Google from the registered name; verify the plot before relying on it.Open in Google Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in Creek Waters 2

Towers inside this project that have enough registered resales for their own record.

More from The Lagoons Phase One

Live projects registered to the same developer, most advanced first.

Ask about Creek Waters 2

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will Creek Waters 2 be completed?
The developer registered handover for December 2027, 17 months after DLD’s latest record, and the project was 47% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
What does Creek Waters 2 cost per square foot?
AED 2,335 per sqft, the median of 46 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 2.48M. That is 10.7% below the Dubai Creek Harbour off-plan median across 19 projects.
Is Creek Waters 2 in escrow?
Yes: the Land Department register names بنك أبوظبي الأول ش.م.ع. as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of Creek Waters 2?
THE LAGOONS PHASE ONE L.L.C, licence no. 1038, by the register’s own licence number; the master developer that owns the land is The Lagoons Phase 1. Dubai Land Department project register as of July 2026.
How many units does Creek Waters 2 have?
455 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send Creek Waters 2 to a client as a branded report

Create client report

Off-plan record for Creek Waters 2

Record type
Project-level off-plan register record
Data date
Evidence base
455 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/dubai-creek-harbour/creek-waters-2
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Creek Waters 2, off-plan.” Dubai Creek Harbour, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-creek-harbour/creek-waters-2