Dubai Harbour Residences (Area 1)
Registered for handover in Q1 2028 and 1% built in July 2026. Off-plan units sell at AED 9.70M (AED 4,560/sqft), 1% above the Dubai Harbour off-plan median.
Off-plan price, typical unit
9.70MAED
AED 4,560/sqft · 1% above Dubai Harbour off-plan · 29 sales in 12 months
Started Feb 2025Registered handover Jan 2028
DLD project register, Jul 2026
- Median off-plan sale
- AED 9.70M
- Titles issued
- 0 of 212
- Escrow
- بنك الإمارات دبي الوطني (ش.م.ع)
Is Dubai Harbour Residences (Area 1) a safe off-plan buy?In escrow; 1% built with 18 months to its registered handover; no record of the builder
- Is it on schedule?1% built in July 2026 against a January 2028 handover: 99% left to build in 18 months · DLD project register, Jul 20261%Context
- Is my money protected?Payments go to an escrow account at بنك الإمارات دبي الوطني (ش.م.ع), as registered with the Land DepartmentEscrowContext
- Is the price fair?AED 4,560/sqft, 1.2% above the Dubai Harbour off-plan median across 14 projects+1.2%Context
- Is it selling?29 off-plan sales registered in the last 12 months, of 212 units; the latest on 20 May 202629Context
- Who is building it?The register names neither the builder nor the master developerNo record
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built212 units, mostly two-beds and three-beds; none titled yet
DLD unit register · balconies a median 19% of unit area · median off-plan sale AED 9.70M
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
212 units in DLD’s register for Dubai Harbour Residences (Area 1), floor by floor.
Show 212 of 212 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Dubai Harbour projects are trackingThe nearest-to-finished are all within their registered dates
“Past date”: the registered date has already passed · 0 of 10 live Dubai Harbour projects past theirs · DLD register and inspections, October 2026
All 19 Dubai Harbour projects →As registered with the Land DepartmentWhere Dubai Harbour Residences (Area 1) is, and who is on its register row
- Escrow agent
- بنك الإمارات دبي الوطني (ش.م.ع)
- Registered start
- February 2025
- Configuration
- Residential and Commercial Building 2B+G+8 Ground, Floor retail public praying facilities
Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in Dubai Harbour Residences (Area 1)
Towers inside this project that have enough registered resales for their own record.
Ask about Dubai Harbour Residences (Area 1)
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will Dubai Harbour Residences (Area 1) be completed?
- The developer registered handover for January 2028, 18 months after DLD’s latest record, and the project was 1% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
- What does Dubai Harbour Residences (Area 1) cost per square foot?
- AED 4,560 per sqft, the median of 29 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 9.70M. That is 1.2% above the Dubai Harbour off-plan median across 14 projects.
- Is Dubai Harbour Residences (Area 1) in escrow?
- Yes: the Land Department register names بنك الإمارات دبي الوطني (ش.م.ع) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- How many units does Dubai Harbour Residences (Area 1) have?
- 212 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send Dubai Harbour Residences (Area 1) to a client as a branded report
Off-plan record for Dubai Harbour Residences (Area 1)
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 212 registered units; DLD project register as of 2026-07-06
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
Cite as: Dubai Wealth Index. “Dubai Harbour Residences (Area 1), off-plan.” Dubai Harbour, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-harbour/dubai-harbour-residences-area-1