Beach Walk Residences 2
Recorded complete in August 2026.
Started Aug 2024Completed Aug 2026
DLD inspection, 4 Aug 2026
- Titles issued
- 63 of 63
- Escrow
- بنك أبوظبي الأول ش.م.ع.
Is Beach Walk Residences 2 a safe off-plan buy?Recorded complete in August 2026
- Is it on schedule?Recorded complete in August 2026, on its registered date to the day: the register often stamps one onto the other · DLD inspection, 4 Aug 2026100%Context
- Is my money protected?The register named the escrow agent: بنك أبوظبي الأول ش.م.ع.EscrowContext
- Is the price fair?Off-plan prices are read across a project’s published towers, and this one has none yetNo record
- Is it selling?Off-plan sales are counted across a project’s published towers, and this one has none yetNo record
- Who is building it?Imtiaz, licence no. 1641; 2 of its 20 dated live projects are past their registered dates10%Context
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built63 units, mostly two-beds; all titled
DLD unit register · balconies a median 19% of unit area
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
63 units in DLD’s register for Beach Walk Residences 2, floor by floor.
Show 63 of 63 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Dubai Islands projects are trackingThe nearest-to-finished are all past their registered dates
“Past date”: the registered date has already passed · 11 of 87 live Dubai Islands projects past theirs · DLD register and inspections, October 2026
All 93 Dubai Islands projects →As registered with the Land DepartmentWhere Beach Walk Residences 2 is, and who is on its register row
- Escrow agent
- بنك أبوظبي الأول ش.م.ع.
- Developer, as licensed
- IMTIAZ GHD REAL ESTATE DEVELOPMENT L.L.C (no. 1641)
- Master developer
- Nakheel
- Registered start
- August 2024
- Configuration
- G+2P+8F+R (Residential Building).The project designed to have a concrete structure and block with internal and external finishes.
Construction progress is DLD’s inspection of 4 Aug 2026. DLD’s published project register still lags it, so the later inspection is used and dated on its own. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
More from Imtiaz
Live projects registered to the same developer, most advanced first.
Cove Edition Residence 1 By Imtiaz
Dubailand Residence Complex · registered handover Aug 2026
90%
built, DLD register
Luxur Tower By Imtiaz
Jumeirah Village Circle · registered handover Dec 2026
90%
built, DLD register
Beach Walk Residences 3 by Imtiaz
Dubai Islands · registered handover Jun 2026
82%
built, DLD register
Sunset Bay One By Imtiaz
Dubai Islands · registered handover Dec 2026
78%
built, DLD register
Ask about Beach Walk Residences 2
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will Beach Walk Residences 2 be completed?
- DLD records Beach Walk Residences 2 complete in August 2026. Dubai Land Department inspection of 4 Aug 2026.
- Is Beach Walk Residences 2 in escrow?
- Yes: the Land Department register names بنك أبوظبي الأول ش.م.ع. as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of Beach Walk Residences 2?
- IMTIAZ GHD REAL ESTATE DEVELOPMENT L.L.C, licence no. 1641, by the register’s own licence number; the master developer that owns the land is Nakheel. Dubai Land Department project register as of July 2026.
- How many units does Beach Walk Residences 2 have?
- 63 registered units, of which 63 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send Beach Walk Residences 2 to a client as a branded report
Off-plan record for Beach Walk Residences 2
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 63 registered units; DLD project register as of 2026-07-06; construction state from the DLD inspection, 4 Aug 2026
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record
- /off-plan/apartments/dubai/dubai-islands/beach-walk-residences-2
Cite as: Dubai Wealth Index. “Beach Walk Residences 2, off-plan.” Dubai Islands, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-islands/beach-walk-residences-2