- Registered projects
- 31
- DLD register, Jul 2026
- Live past their registered date
- 9%
- 2 of 23 live projects with dates · 5 without dates
- Median slippage
- —
- 0 measurable completions
- Completed
- 3
- 3 dated to the registered day
Every project the Dubai Land Department registers to Imtiaz, matched by the developer licence number on each registration across the 6 licensed companies this name covers — a high-confidence identity. A live project past the completion date the developer itself registered is counted as overdue, not as late: it has not been delivered yet, and this site does not forecast when it will be.
The register dates 3 of this developer’s 3 completed projects to the registered day exactly — it writes the completion date onto the planned one — so those show no slippage in either direction and are excluded from the figure above rather than counted as delivered on time. That leaves 0 measurable completions, too few to publish a median.
Live projects
28 registered and not yet recorded complete, most advanced first.
Delivered projects
3 recorded complete, most recent first. Slippage is months from the registered date to the recorded one; negative is early.
Imtiaz, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 31 registered projects, 28 live of which 2 past their registered date, 0 completions with a measurable slippage of 3 completed; DLD project register as of 2026-07-06; identity high-confidence over 6 licensed companies
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/imtiaz
Cite as: Dubai Wealth Index. “Imtiaz, delivery record.” Register to 2026-07-06, data to 2026-09-11. https://dubaiwealthindex.com/developers/imtiaz