Hamilton House
Recorded complete in January 2025.
Started Dec 2022Completed Jan 2025
DLD project register, Jul 2026
- Titles issued
- 101 of 101
- Escrow
- بنك ابوظبى التجارى
Saves the tower’s record to your account.
Is Hamilton House a safe off-plan buy?Recorded complete in January 2025
- Is it on schedule?Recorded complete in January 2025, on its registered date to the day: the register often stamps one onto the other · DLD project register, Jul 2026100%Context
- Is my money protected?The register named the escrow agent: بنك ابوظبى التجارىEscrowContext
- Is the price fair?No off-plan sale registered in 12 months to price it onNo record
- Is it selling?No off-plan sale registered in 12 months; the last in February 20250Context
- Who is building it?Ellington Properties, licence no. 1117; 3 of its 13 dated live projects are past their registered dates23%Context
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built101 units, mostly one-beds; all titled
DLD unit register · balconies a median 12% of unit area
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
101 units in DLD’s register for Hamilton House, floor by floor.
Show 101 of 101 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Jumeirah Village Circle projects are trackingThe nearest-to-finished are all past their registered dates
“Past date”: the registered date has already passed · 40 of 99 live Jumeirah Village Circle projects past theirs · DLD register and inspections, October 2026
All 297 Jumeirah Village Circle projects →As registered with the Land DepartmentWhere Hamilton House is, and who is on its register row
- Escrow agent
- بنك ابوظبى التجارى
- Developer, as licensed
- ELLINGTON PROPERTIES DEVELOPMENT L.L.C (no. 1117)
- Master developer
- Jumeirah Village
- Registered start
- December 2022
- Configuration
- Residential Building (G+1P+5F).The project designed to have a concrete structure and block with internal and external finishes.
Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in Hamilton House
Towers inside this project that have enough registered resales for their own record.
More from Ellington Properties
Live projects registered to the same developer, most advanced first.
Uh West by Ellington
Jumeirah Lake Towers · registered handover Mar 2026
71%
built, DLD register
Uh East by Ellington
Jumeirah Lake Towers · registered handover Mar 2026
47%
built, DLD register
The Highbury
Sobha Hartland · no registered handover date
37%
built, DLD register
The Portman
Jumeirah Village Circle · registered handover Sept 2025
37%
built, DLD register
Ask about Hamilton House
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will Hamilton House be completed?
- The register records Hamilton House complete in January 2025. Dubai Land Department project register as of July 2026.
- Is Hamilton House in escrow?
- Yes: the Land Department register names بنك ابوظبى التجارى as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of Hamilton House?
- ELLINGTON PROPERTIES DEVELOPMENT L.L.C, licence no. 1117, by the register’s own licence number; the master developer that owns the land is Jumeirah Village. Dubai Land Department project register as of July 2026.
- How many units does Hamilton House have?
- 101 registered units, of which 101 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send Hamilton House to a client as a branded report
Off-plan record for Hamilton House
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 101 registered units; DLD project register as of 2026-07-06
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
Cite as: Dubai Wealth Index. “Hamilton House, off-plan.” Jumeirah Village Circle, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/jumeirah-village-circle/hamilton-house