Ellington Properties
3 of Ellington’s 13 dated live projects are past the completion date it registered itself: 23%, against 13% across the 28 Dubai developers with ten or more registered projects. Its most-traded tower, Eltiera Heights, registered 300 sales in the last 12 months at a median AED 2.29M (AED 2,539/sqft).
Live projects past their registered date
23%3 of 13
28 developers with ten or more projects: 13%
- Registered projects
- 33
- Completed
- 16
- Live, no registered date
- 4
Does Ellington deliver on time?More of its live projects are past their own dates than Dubai’s share; its most-traded tower sells at a typical AED 2.29M (AED 2,539/sqft)
- Are live projects on time?3 of 13 dated live projects are past the date Ellington registered; 4 more carry no date23%Context
- How does it rank?18th of the 22 developers ranked on delivery, fewest overdue first; Dubai’s share past date is 13%18thContext
- How late, typically?Only 1 completion carries a date distinct from the plan: 14 of 16 were stamped with itNo record
- Do its towers trade?Eltiera Heights trades at AED 2,539/sqft on 300 sales, off-plan and ready, in 12 months; 34 of its towers have a sale recordAED 2.29MContext
Ranked on the share of live projects past their own registered date · fewest first · register Jul 2026
Live projects, most advanced firstUh West by Ellington is 71% built and 3 months past its date
Built % and dates from the DLD register, Jul 2026 · months past date at that register date · a live project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be
Delivered projects, most recent first16 completed, 14 dated to the registered day
Show the 16 delivered projectsHide the delivered projects
Slippage is months from the registered date to the recorded one; negative is early. The register dates 14 of these 16 completions to the registered day exactly — it writes the completion date onto the planned one — so those are marked “stamped” and left out of the median rather than counted as on time. 1 measurable completion is too few to publish a median (the floor is 5).
Ellington towers on the marketIts towers trade between AED 1,281 and 2,713 per sqft
Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 34
Every project the Dubai Land Department registers to Ellington Properties, matched by the developer licence number on each registration across the 2 licensed companies this name covers — a high-confidence identity.
Common questions
- Are Ellington's off-plan projects on time?
- 3 of Ellington's 13 dated live projects are past the completion date the developer registered itself (23%), against 13% across the 28 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-07-06.
- How does Ellington rank against other Dubai developers on delivery?
- Ellington ranks 18th of the 22 developers ranked on delivery, fewest live projects past their registered date first. Only developers with at least 5 live projects are ranked. Dubai Land Department project register to 2026-07-06.
- How late are Ellington's completed projects, typically?
- Not enough to say: only 1 of its 16 completed projects carries a completion date distinct from the registered one, so no median slippage is published. Dubai Land Department project register to 2026-07-06.
- How many projects has Ellington registered in Dubai?
- 33 registered projects: 17 live, 16 completed. Projects are matched to Ellington Properties by the developer licence number on each registration. Dubai Land Department project register to 2026-07-06.
- What do Ellington's towers sell for?
- Its most-traded tower, Eltiera Heights, sold at a median AED 2,539/sqft across 300 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.
For agents
Send Ellington’s delivery record to a client
Ellington Properties, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 33 registered projects, 17 live of which 3 past their registered date, 1 completions with a measurable slippage of 16 completed; DLD project register as of 2026-07-06; identity high-confidence over 2 licensed companies
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/ellington-properties
Cite as: Dubai Wealth Index. “Ellington Properties, delivery record.” Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/developers/ellington-properties