Off-plan · DLD project register as of 6 Jul 2026

One Crescent

Under construction · 25 units · started May 2023 · Palm Jumeirah

Registered for handover in Q1 2026 and 80% built in July 2026, 4 months past that date.

Built80%

Started May 2023Registered handover Mar 2026 · overdue

DLD inspection, 23 Jul 2026

Titles issued
0 of 25
Escrow
بنك دبي الاسلامي (شركة مساهمة عامة)

Is One Crescent a safe off-plan buy?In escrow; 80% built and 4 months past its registered handover; no record of off-plan sales

  1. Is it on schedule?80% built in July 2026, 4 months past its registered March 2026 handover · DLD inspection, 23 Jul 202680%Context
  2. Is my money protected?Payments go to an escrow account at بنك دبي الاسلامي (شركة مساهمة عامة), as registered with the Land DepartmentEscrowContext
  3. Is the price fair?Off-plan prices are read across a project’s published towers, and this one has none yetNo record
  4. Is it selling?Off-plan sales are counted across a project’s published towers, and this one has none yetNo record
  5. Who is building it?A H S Palm, licence no. 1492Context

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

How each reading works →

What is being built25 units, mostly three-beds; none titled yet

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
3 bed143,738–4,5100
4+ bed115,365–16,5940

DLD unit register · balconies a median 37% of unit area

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

25 units in DLD’s register for One Crescent, floor by floor.

Show 25 of 25 units
FloorUnitTypeSqftBalconyTitle issued
11 · 1013 bed4,6011,784Not yet
11 · 1023 bed4,0041,634Not yet
11 · 1033 bed3,9861,615Not yet
11 · 1043 bed4,2981,481Not yet
21 · 2014+ bed7,6722,821Not yet
21 · 2024+ bed5,3651,840Not yet
21 · 2034+ bed7,6742,823Not yet
31 · 3013 bed3,7381,377Not yet
31 · 3023 bed4,0241,664Not yet
41 · 4014+ bed7,6762,825Not yet

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Palm Jumeirah projects are tracking1 of the 3 nearest-to-finished are past their registered dates

ProjectBuilt%Registered date
Ava at Palm Jumeirah by Omniyat96%Dec 2025 · past date
Palm Beach Towers -183%Dec 2026
Palm Beach Towers - 282%Dec 2026
One Crescentthis project80%Mar 2026 · past date

“Past date”: the registered date has already passed · 5 of 14 live Palm Jumeirah projects past theirs · DLD register and inspections, October 2026

All 47 Palm Jumeirah projects →

As registered with the Land DepartmentWhere One Crescent is, and who is on its register row

Escrow agent
بنك دبي الاسلامي (شركة مساهمة عامة)
Developer, as licensed
A H S PALM DEVELOPMENT L.L.C (no. 1492)
Master developer
Palm Jumeirah LLC
Registered start
May 2023
Configuration
Residential Building (B+G+9+R).The project designed to have a concrete structure and block with internal and external finishes.
Pinned by Google from the registered name; verify the plot before relying on it.Open in Google Maps

Construction progress is DLD’s inspection of 23 Jul 2026. DLD’s published project register still lags it, so the later inspection is used and dated on its own. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Ask about One Crescent

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will One Crescent be completed?
The developer registered handover for March 2026; that date has passed with no completion recorded, 4 months on, and the project was 80% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department inspection of 23 Jul 2026.
Is One Crescent in escrow?
Yes: the Land Department register names بنك دبي الاسلامي (شركة مساهمة عامة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of One Crescent?
A H S PALM DEVELOPMENT L.L.C, licence no. 1492, by the register’s own licence number; the master developer that owns the land is Palm Jumeirah LLC. Dubai Land Department project register as of July 2026.
How many units does One Crescent have?
25 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send One Crescent to a client as a branded report

Create client report

Off-plan record for One Crescent

Record type
Project-level off-plan register record
Data date
Evidence base
25 registered units; DLD project register as of 2026-07-06; construction state from the DLD inspection, 23 Jul 2026
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/palm-jumeirah/one-crescent
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “One Crescent, off-plan.” Palm Jumeirah, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/palm-jumeirah/one-crescent