Jaddaf Waterfront upcoming supply
Every pending apartment project in Jaddaf Waterfront, by when it is due, set against the homes let there today. Prices and yields in Jaddaf Waterfront · Off-plan launches
- Data to
- Pending projects
- 12
- Pending units
- 1,824
Jaddaf Waterfront: 733 apartments planned for 2026–2028, 53% of the homes let there today
Counted against today, 2026-10-18. Register to 2026-07-06; leases to 2026-10-12.
- Planned 2026–28
- 733
- 1,824 pending in all
- Homes let today
- 1,395
- Ejari tenancies in force
- Planned ÷ homes let
- 53%
- 0.5× a year of leasing
- Due in 12 months
- 658
- 464 already past their date
When it is due
Every pending apartment, by its registered completion quarter.
Handover calendar
Apartment units, by planned completion quarter
- Late: 464464
- Q4 ’26: 240240
- Q1 ’27: 4444
- Q2 ’27: 121121
- Q3 ’27: 253253
- Q4 ’27: 7575
- Q1 ’28: 00
- Q2 ’28: 00
- Q3 ’28: 00
- Q4 ’28: 00
- No date: 627627
Which homes, against which lets
Planned for 2026–2028 by bedroom type, against the homes of that type let today.
Planned apartments
Units due 2026–2028, by bedroom type
- Studio111
- 1 bed401
- 2 bed191
- 3 bed30
- 4+ bed0
Planned as a share of homes let today
Planned units ÷ registered tenancies in force
- Studio63%
- 1 bed84%
- 2 bed35%
- 3 bed16%
How the pressure has moved
Each point is one monthly report: the same measure, recomputed for that month's end.
Planned supply as a share of homes let
Planned units for the next three calendar years ÷ tenancies in force, %
Project calendar
12 pending projects, 1,824 units. Progress is the register's reported share built.
Planned date passed464 units · 2 projects
- Binghatti Twilight2026-04-3022855%
- Binghatti Moonlight2026-06-1523619%
2026 Q4240 units · 2 projects
- Val by Kasco2026-12-3012173%
- La Boutique2026-12-3111953%
2027 Q144 units · 1 project
- Celeste2027-02-28440%
2027 Q2121 units · 1 project
- Lumiere Heights2027-06-301210%
2027 Q3253 units · 1 project
- Montage2027-08-312533%
2027 Q475 units · 1 project
- Amazonia2027-10-30750%
No planned date627 units · 4 projects
- Boutique 23No planned date25317%
- Art Bay WestNo planned date1676%
- Creek ViewsNo planned date10811%
- Art Bay EastNo planned date994%
Method and limits
Planned supply is every apartment unit in a project the Land Department register lists as neither complete nor cancelled, placed by its registered completion date and counted against today. Homes let today are the registered Ejari tenancies in force on the data date. A planned date is the developer's, not a delivery forecast; completions slip, and some homes are owner-occupied or let short-term.
Why tenancies and not the register: the unit register only reaches back to recently registered projects, so it misses most of the homes standing today. Ejari records every registered lease with its start and end. Full methodology
Jaddaf Waterfront upcoming apartment supply
- Record type
- Planned supply against tenancies
- Data date
- Evidence base
- 1,824 pending apartment units in 12 projects; 1,395 tenancies in force
- Sources
- Dubai Land Department project and unit registers; Ejari tenancies