Wasl Gate upcoming supply

Every pending apartment project in Wasl Gate, by when it is due, set against the homes let there today. Prices and yields in Wasl Gate · Off-plan launches

Data to
Pending projects
13
Pending units
3,596

Wasl Gate: 2,525 apartments planned for 2026–2028, 636% of the homes let there today

Counted against today, 2026-10-18. Register to 2026-07-06; leases to 2026-10-12.

Planned 2026–28
2,525
3,596 pending in all
Homes let today
397
Ejari tenancies in force
Planned ÷ homes let
636%
6.2× a year of leasing
Due in 12 months
260
0 already past their date

When it is due

Every pending apartment, by its registered completion quarter.

Handover calendar

Apartment units, by planned completion quarter

  1. Q4 ’26: 0
  2. Q1 ’27: 0
  3. Q2 ’27: 0
  4. Q3 ’27: 260
  5. Q4 ’27: 1.4k
  6. Q1 ’28: 0
  7. Q2 ’28: 862
  8. Q3 ’28: 0
  9. Q4 ’28: 0
  10. No date: 1.1k
Grey: late (planned date passed), after the three-year window, or no date. A planned date is the developer's registered date, not a delivery forecast. Source: DLD project and unit registers.

Which homes, against which lets

Planned for 2026–2028 by bedroom type, against the homes of that type let today.

Planned apartments

Units due 2026–2028, by bedroom type

  1. Studio479
  2. 1 bed961
  3. 2 bed971
  4. 3 bed114
  5. 4+ bed0
Source: DLD unit register.

Planned as a share of homes let today

Planned units ÷ registered tenancies in force

  1. 1 bed898%
  2. 2 bed426%
100% means as many new homes are planned as are let today. Types with fewer than 100 homes let are left out. Sources: DLD unit register, Ejari.

How the pressure has moved

Each point is one monthly report: the same measure, recomputed for that month's end.

Planned supply as a share of homes let

Planned units for the next three calendar years ÷ tenancies in force, %

620%630%640%650%JanMarMayJulSepPlanned ÷ homes let, Jan: 647%Planned ÷ homes let, Feb: 639%Planned ÷ homes let, Mar: 627%Planned ÷ homes let, Apr: 633%Planned ÷ homes let, May: 634%Planned ÷ homes let, Jun: 643%Planned ÷ homes let, Jul: 633%Planned ÷ homes let, Aug: 633%Planned ÷ homes let, Sep: 639%639%
The window moves with the calendar year, so a step in January is the window rolling forward. Sources: DLD unit register, Ejari.

Project calendar

13 pending projects, 3,596 units. Progress is the register's reported share built.

2027 Q3260 units · 1 project

2027 Q41,403 units · 5 projects

2028 Q2862 units · 3 projects

No planned date1,071 units · 4 projects

Method and limits

Planned supply is every apartment unit in a project the Land Department register lists as neither complete nor cancelled, placed by its registered completion date and counted against today. Homes let today are the registered Ejari tenancies in force on the data date. A planned date is the developer's, not a delivery forecast; completions slip, and some homes are owner-occupied or let short-term.

Why tenancies and not the register: the unit register only reaches back to recently registered projects, so it misses most of the homes standing today. Ejari records every registered lease with its start and end. Full methodology

Wasl Gate upcoming apartment supply

Record type
Planned supply against tenancies
Data date
Evidence base
3,596 pending apartment units in 13 projects; 397 tenancies in force
Sources
Dubai Land Department project and unit registers; Ejari tenancies
Canonical record
/supply/apartments/dubai/wasl-gate
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Wasl Gate upcoming apartment supply.” Wasl Gate, Dubai. Data to 2026-10-12. https://dubaiwealthindex.com/supply/apartments/dubai/wasl-gate