Dubai Hills Estate, delivery record
- Edition DWI-DEVELOPER-DUBAI-HILLS-ESTATE
- Registered projects
- 51
- DLD register, Jul 2026
- Delivered on time
- 95%
- of 22 completed
- Median slippage
- 0months
- registered date to recorded completion
- Live and overdue
- 4
- of 29 live
Every project the Dubai Land Department registers to دبي هيلز استيت ش.ذ.م.م, which this site publishes as Dubai Hills Estate — a high-confidence reading of the registered Arabic name. On-time delivery and slippage are measured on completed projects against the completion date the developer itself registered. A live project past that date is counted as overdue, not as late: it has not been delivered yet, and this site does not forecast when it will be.
Live projects
29 registered and not yet recorded complete, most advanced first.
Delivered projects
22 recorded complete, most recent first. Slippage is months from the registered date to the recorded one; negative is early.
Dubai Hills Estate, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 51 registered projects, 22 completed; DLD project register as of 2026-07-06; identity high-confidence
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/dubai-hills-estate
Cite as: Dubai Wealth Index. “Dubai Hills Estate, delivery record.” Register to 2026-07-06, data to 2026-08-26. https://dubaiwealthindex.com/developers/dubai-hills-estate.