The central downtown

Under construction · 1,177 units · started Nov 2023 · Arjan

Registered for handover in Q1 2028 and 4% built in July 2026. Off-plan units sell at AED 1.08M (AED 1,424/sqft), 15% below the Arjan off-plan median.

Off-plan price, typical unit

1.08MAED

AED 1,424/sqft · 15% below Arjan off-plan · 144 sales in 12 months

Built4%

Started Nov 2023Registered handover Mar 2028

DLD project register, Jul 2026

Median off-plan sale
AED 1.08M
Titles issued
0 of 1,177
Escrow
بنك أبوظبي الأول ش.م.ع.

Is The central downtown a safe off-plan buy?In escrow; 4% built with 20 months to its registered handover; no record of the builder

  1. Is it on schedule?4% built in July 2026 against a March 2028 handover: 96% left to build in 20 months · DLD project register, Jul 20264%Context
  2. Is my money protected?Payments go to an escrow account at بنك أبوظبي الأول ش.م.ع., as registered with the Land DepartmentEscrowContext
  3. Is the price fair?AED 1,424/sqft, 14.7% below the Arjan off-plan median across 35 projects-14.7%Context
  4. Is it selling?144 off-plan sales registered in the last 12 months, of 1,177 units; the latest on 30 Sept 2026144Context
  5. Who is building it?The register names the master developer, Liwan; the builder is not recordedNo record

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

How each reading works →

What is being built1,177 units, mostly one-beds and studios; none titled yet

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
Studio351439–4960
1 bed528714–9010
2 bed1941,118–1,4540
3 bed1042,149–2,2050

DLD unit register · balconies a median 18% of unit area · median off-plan sale AED 1.08M

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

1,177 units in DLD’s register for The central downtown, floor by floor.

Show 400 of 1,177 units
FloorUnitTypeSqftBalconyTitle issued
21 · A2012 bed1,460333Not yet
21 · A202Studio47584Not yet
21 · A203Studio48885Not yet
21 · A2041 bed789135Not yet
21 · A2052 bed1,233336Not yet
21 · A2061 bed1,010304Not yet
21 · A2071 bed762130Not yet
21 · A2081 bed762130Not yet
21 · A209Studio47683Not yet
21 · A2102 bed1,176144Not yet

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Arjan projects are tracking2 of the 3 nearest-to-finished are past their registered dates

ProjectBuilt%Registered date
Samana Mykonos Signature86%Apr 2026 · past date
Rose Gardens 376%May 2026 · past date
One Beverly73%Dec 2026
The central downtownthis project4%Mar 2028

“Past date”: the registered date has already passed · 6 of 18 live Arjan projects past theirs · DLD register and inspections, October 2026

All 70 Arjan projects →

As registered with the Land DepartmentWhere The central downtown is, and who is on its register row

Escrow agent
بنك أبوظبي الأول ش.م.ع.
Master developer
Liwan
Registered start
November 2023
Configuration
MIXED USE BUILDING (G + 2P + 26 FLOORS + ROOF) at ARJAN .The project designed to have a concrete structure and block with internal and external finishes.
Pills show median resale price per sqft, AED. 4 of 4 published towers pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in The central downtown

Towers inside this project that have enough registered resales for their own record.

Ask about The central downtown

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will The central downtown be completed?
The developer registered handover for March 2028, 20 months after DLD’s latest record, and the project was 4% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
What does The central downtown cost per square foot?
AED 1,424 per sqft, the median of 144 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 1.08M. That is 14.7% below the Arjan off-plan median across 35 projects.
Is The central downtown in escrow?
Yes: the Land Department register names بنك أبوظبي الأول ش.م.ع. as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of The central downtown?
The register names the master developer, Liwan, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
How many units does The central downtown have?
1,177 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send The central downtown to a client as a branded report

Create client report

Off-plan record for The central downtown

Record type
Project-level off-plan register record
Data date
Evidence base
1,177 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/arjan/the-central-downtown
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “The central downtown, off-plan.” Arjan, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/arjan/the-central-downtown