The Community Motor City
Registered for handover in Q4 2025 and 50% built in July 2026, 9 months past that date. Off-plan units sell at AED 750,000 (AED 1,386/sqft), 26% below the Motor City off-plan median.
Off-plan price, typical unit
750,000AED
AED 1,386/sqft · 26% below Motor City off-plan · 39 sales in 12 months
Started Nov 2022Registered handover Oct 2025 · overdue
DLD project register, Jul 2026
- Median off-plan sale
- AED 750,000
- Titles issued
- 0 of 414
- Escrow
- بنك المشرق (شركة مساهمة عامة)
Saves the tower’s record to your account.
Is The Community Motor City a safe off-plan buy?In escrow; 50% built and 9 months past its registered handover; no record of the builder
- Is it on schedule?50% built in July 2026, 9 months past its registered October 2025 handover · DLD project register, Jul 202650%Context
- Is my money protected?Payments go to an escrow account at بنك المشرق (شركة مساهمة عامة), as registered with the Land DepartmentEscrowContext
- Is the price fair?AED 1,386/sqft, 26.3% below the Motor City off-plan median across 11 projects-26.3%Context
- Is it selling?39 off-plan sales registered in the last 12 months, of 414 units; the latest on 14 Sept 202639Context
- Who is building it?The register names the master developer, Union Properties; the builder is not recordedNo record
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built414 units, mostly studios and one-beds; none titled yet
DLD unit register · balconies a median 11% of unit area · median off-plan sale AED 750,000
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
414 units in DLD’s register for The Community Motor City, floor by floor.
Show 400 of 414 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Motor City projects are trackingThe nearest-to-finished are all within their registered dates
“Past date”: the registered date has already passed · 1 of 9 live Motor City projects past theirs · DLD register and inspections, October 2026
All 11 Motor City projects →As registered with the Land DepartmentWhere The Community Motor City is, and who is on its register row
- Escrow agent
- بنك المشرق (شركة مساهمة عامة)
- Master developer
- Union Properties
- Registered start
- November 2022
- Configuration
- G+P+6+R Residential+Retail.The project designed to have a concrete structure and block with internal and external finishes.
Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in The Community Motor City
Towers inside this project that have enough registered resales for their own record.
Ask about The Community Motor City
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will The Community Motor City be completed?
- The developer registered handover for October 2025; that date has passed with no completion recorded, 9 months on, and the project was 50% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
- What does The Community Motor City cost per square foot?
- AED 1,386 per sqft, the median of 39 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 750,000. That is 26.3% below the Motor City off-plan median across 11 projects.
- Is The Community Motor City in escrow?
- Yes: the Land Department register names بنك المشرق (شركة مساهمة عامة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of The Community Motor City?
- The register names the master developer, Union Properties, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
- How many units does The Community Motor City have?
- 414 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send The Community Motor City to a client as a branded report
Off-plan record for The Community Motor City
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 414 registered units; DLD project register as of 2026-07-06
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record