Data to
Creek Haven
Registered for handover in Q1 2030 and 1% built in November 2026.
- Built
- 1%
- Registered handover Mar 2030
- Typical unit, off-plan
- AED 1.99M
- AED 2,686/sqft · 473 sales in 12 months
- Against Dubai Creek Harbour
- +3%
- Off-plan median per sqft, 18 projects
- Registered units
- 593
- 0 with a title issued
Off-plan price, typical unit
1.99M AED
AED 2,686/sqft · 3% above Dubai Creek Harbour off-plan · 473 sales in 12 months
Started Mar 2026Registered handover Mar 2030
DLD project register, Nov 2026
Project alerts are being built for Pro.
Register interest in alerts on Creek Haven’s progress and handover date.
- Median off-plan sale
- AED 1.99M
- Titles issued
- 0 of 593
- Escrow
- بنك ابوظبى التجارى
Escrow, progress and price In escrow; 1% built with 40 months to its registered handover
- Is it on schedule?1% built in November 2026 against a March 2030 handover: 99% left to build in 40 months · DLD project register, Nov 20261%Context
- Is my money protected?Payments go to an escrow account at بنك ابوظبى التجارى, as registered with the Land DepartmentEscrowContext
- Is the price fair?AED 2,686/sqft, 2.6% above the Dubai Creek Harbour off-plan median across 18 projects+2.6%Context
- Is it selling?473 off-plan sales registered in the last 12 months, of 593 units; the latest on 29 Oct 2026473Context
- Who is building it?Dubai Creek Harbour, licence no. 1224; 0 of its 11 dated pending projects are past their registered dates0%Context
A registered date is not a delivery forecast · 67% of recorded completions carry their planned date to the day · DLD register, November 2026
What is being built593 units, mostly two-beds and one-beds; none titled yet
DLD unit register · balconies a median 14% of unit area · median off-plan sale AED 1.99M
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a pending project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
593 units in DLD’s register for Creek Haven, floor by floor.
Show 400 of 593 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Dubai Creek Harbour projects are trackingThe nearest-to-finished are all within their registered dates
“Past date”: the registered date has already passed · 0 of 13 pending Dubai Creek Harbour projects past theirs · DLD register and inspections, November 2026
All 48 Dubai Creek Harbour projects →As registered with the Land DepartmentWhere Creek Haven is, and who is on its register row
- Escrow agent
- بنك ابوظبى التجارى
- Developer, as licensed
- DUBAI CREEK HARBOUR L.L.C (no. 1224)
- Master developer
- Dubai Creek Harbour LLC
- Registered start
- March 2026
- Configuration
- The project is a multi-story residential building consisting of Basement, ground floor with an attached nursery, 3 podium levels Tower(A) - 30 floors Roof level With Total Residential Units 274
Construction progress is the percentage DLD recorded in its project register as of November 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in Creek Haven
Towers inside this project that have enough registered resales for their own record.
More from Dubai Creek Harbour
Pending projects registered to the same developer, most advanced first.
Aeon
Dubai Creek Harbour · no registered handover date
90%
built, DLD register
Oria
Dubai Creek Harbour · no registered handover date
71%
built, DLD register
Valo
Dubai Creek Harbour · no registered handover date
66%
built, DLD register
Altus
Dubai Creek Harbour · registered handover Jan 2029
64%
built, DLD register
Ask an agent about Creek Haven
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When is Creek Haven handed over?
- The developer registered handover for March 2030, 40 months after DLD’s latest record, and the project was 1% built as of November 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of November 2026.
- How far along is construction of Creek Haven?
- Creek Haven was 1% built as of November 2026, the Land Department’s recorded progress, not a developer claim. Dubai Land Department project register as of November 2026.
- Who is the developer of Creek Haven?
- DUBAI CREEK HARBOUR L.L.C, licence no. 1224, by the register’s own licence number; the master developer that owns the land is Dubai Creek Harbour LLC. Dubai Land Department project register as of November 2026.
- What does Creek Haven cost per square foot?
- AED 2,686 per sqft, the median of 473 registered off-plan sales in the 12 months to 2 Nov 2026; the median unit sold for AED 1.99M. That is 2.6% above the Dubai Creek Harbour off-plan median across 18 projects.
- Is Creek Haven in escrow?
- Yes: the Land Department register names بنك ابوظبى التجارى as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of November 2026.
- How many units does Creek Haven have?
- 593 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of November 2026.
Send Creek Haven to a client as a branded report
Create client reportOff-plan record for Creek Haven
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 593 registered units; DLD project register as of 2026-11-01
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record
- /off-plan/apartments/dubai/dubai-creek-harbour/creek-haven
Cite as: Dubai Wealth Index. “Creek Haven, off-plan.” Dubai Creek Harbour, Dubai. Register to 2026-11-01, data to 2026-11-02. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-creek-harbour/creek-haven