Dubai Creek Harbour
None of Dubai Creek Harbour’s 8 dated live projects is past the completion date it registered itself: 0%, against 13% across the 28 Dubai developers with ten or more registered projects. Its most-traded tower, Lyvia by Palace, registered 463 sales in the last 12 months at a median AED 2.93M (AED 2,673/sqft).
Live projects past their registered date
0%0 of 8
28 developers with ten or more projects: 13%
- Registered projects
- 24
- Completed
- 12
- Live, no registered date
- 4
Does Dubai Creek Harbour deliver on time?No dated live project is past its own registered date; its most-traded tower sells at a typical AED 2.93M (AED 2,673/sqft)
- Are live projects on time?0 of 8 dated live projects are past the date Dubai Creek Harbour registered; 4 more carry no date0%Context
- How does it rank?8th of the 22 developers ranked on delivery, fewest overdue first; Dubai’s share past date is 13%8thContext
- How late, typically?Only 2 completions carry a date distinct from the plan: 10 of 12 were stamped with itNo record
- Do its towers trade?Lyvia by Palace trades at AED 2,673/sqft on 463 sales, off-plan and ready, in 12 months; 53 of its towers have a sale recordAED 2.93MContext
Ranked on the share of live projects past their own registered date · fewest first · register Jul 2026
Live projects, most advanced first12 live projects, none past their registered date
Built % and dates from the DLD register, Jul 2026 · months past date at that register date · a live project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be
Delivered projects, most recent first12 completed, 10 dated to the registered day
Show the 12 delivered projectsHide the delivered projects
Slippage is months from the registered date to the recorded one; negative is early. The register dates 10 of these 12 completions to the registered day exactly — it writes the completion date onto the planned one — so those are marked “stamped” and left out of the median rather than counted as on time. 2 measurable completions are too few to publish a median (the floor is 5).
Dubai Creek Harbour towers on the marketIts towers trade between AED 1,811 and 2,989 per sqft
Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 53
Every project the Dubai Land Department registers to Dubai Creek Harbour, matched by the developer licence number on each registration — a medium-confidence identity.
Common questions
- Are Dubai Creek Harbour's off-plan projects on time?
- 0 of Dubai Creek Harbour's 8 dated live projects are past the completion date the developer registered itself (0%), against 13% across the 28 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-07-06.
- How does Dubai Creek Harbour rank against other Dubai developers on delivery?
- Dubai Creek Harbour ranks 8th of the 22 developers ranked on delivery, fewest live projects past their registered date first. Only developers with at least 5 live projects are ranked. Dubai Land Department project register to 2026-07-06.
- How late are Dubai Creek Harbour's completed projects, typically?
- Not enough to say: only 2 of its 12 completed projects carry a completion date distinct from the registered one, so no median slippage is published. Dubai Land Department project register to 2026-07-06.
- How many projects has Dubai Creek Harbour registered in Dubai?
- 24 registered projects: 12 live, 12 completed. Projects are matched to Dubai Creek Harbour by the developer licence number on each registration. Dubai Land Department project register to 2026-07-06.
- What do Dubai Creek Harbour's towers sell for?
- Its most-traded tower, Lyvia by Palace, sold at a median AED 2,673/sqft across 463 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.
For agents
Send Dubai Creek Harbour’s delivery record to a client
Dubai Creek Harbour, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 24 registered projects, 12 live of which 0 past their registered date, 2 completions with a measurable slippage of 12 completed; DLD project register as of 2026-07-06; identity medium-confidence over 1 licensed company
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/dubai-creek-harbour
Cite as: Dubai Wealth Index. “Dubai Creek Harbour, delivery record.” Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/developers/dubai-creek-harbour