Skip to content
Dubai Wealth Index
Search
Search areas, projects and buildings by name.
Off-plan · DLD project register as of 6 Jul 2026

Al Haseen Residence

Completed 2020 · 138 units · started May 2017 · Dubai Industrial City

Recorded complete in April 2020.

Built100%

Started May 2017Completed Apr 2020

DLD project register, Jul 2026

Titles issued
138 of 138
Escrow
بنك المشرق (شركة مساهمة عامة)

Saves the tower’s record to your account.

Is Al Haseen Residence a safe off-plan buy?Recorded complete in April 2020

  1. Is it on schedule?Recorded complete in April 2020, on its registered date to the day: the register often stamps one onto the other · DLD project register, Jul 2026100%Context
  2. Is my money protected?The register named the escrow agent: بنك المشرق (شركة مساهمة عامة)EscrowContext
  3. Is the price fair?No off-plan sale registered in 12 months to price it onNo record
  4. Is it selling?No off-plan sale registered in 12 months; the last in July 20200Context
  5. Who is building it?Dugasta, licence no. 1157Context

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

Check an asking price →How each reading works →

What is being built138 units, mostly one-beds and studios; all titled

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
Studio42341–54642
1 bed60729–75360
2 bed36876–1,15136

DLD unit register · balconies a median 14% of unit area

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

138 units in DLD’s register for Al Haseen Residence, floor by floor.

Show 138 of 138 units
FloorUnitTypeSqftBalconyTitle issued
11 · 1012 bed874147Yes
11 · 1022 bed987249Yes
11 · 1031 bed753101Yes
11 · 1041 bed753101Yes
11 · 1051 bed727101Yes
11 · 1062 bed938200Yes
11 · 107Studio34148Yes
11 · 108Studio533104Yes
11 · 1091 bed752101Yes
11 · 1101 bed74199Yes

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Dubai Industrial City projects are trackingThe nearest-to-finished are all within their registered dates

ProjectBuilt%Registered date
Al Haseen Residence 412%Dec 2026
Al Haseen Residence 31%May 2027
Coventry Residence0%Nov 2027

“Past date”: the registered date has already passed · 0 of 7 live Dubai Industrial City projects past theirs · DLD register and inspections, October 2026

All 9 Dubai Industrial City projects →

As registered with the Land DepartmentWhere Al Haseen Residence is, and who is on its register row

Escrow agent
بنك المشرق (شركة مساهمة عامة)
Developer, as licensed
DUGASTA PROPERTIES DEVELOPMENT L.L.C (no. 1157)
Registered start
May 2017
Configuration
PROJECT CONSISTS OF G+6+2R RESIDENTIAL BUILDING LOCATED IN SAIH SHUAIB 2. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.
Pills show median resale price per sqft, AED. 1 of 1 published tower pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in Al Haseen Residence

Towers inside this project that have enough registered resales for their own record.

Ask about Al Haseen Residence

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will Al Haseen Residence be completed?
The register records Al Haseen Residence complete in April 2020. Dubai Land Department project register as of July 2026.
Is Al Haseen Residence in escrow?
Yes: the Land Department register names بنك المشرق (شركة مساهمة عامة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of Al Haseen Residence?
DUGASTA PROPERTIES DEVELOPMENT L.L.C, licence no. 1157, by the register’s own licence number. Dubai Land Department project register as of July 2026.
How many units does Al Haseen Residence have?
138 registered units, of which 138 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send Al Haseen Residence to a client as a branded report

Create client report

Off-plan record for Al Haseen Residence

Record type
Project-level off-plan register record
Data date
Evidence base
138 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/dubai-industrial-city/al-haseen-residence
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Al Haseen Residence, off-plan.” Dubai Industrial City, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-industrial-city/al-haseen-residence