Ciel

Under construction · 1,019 units · started Nov 2016 · Dubai Marina

Registered for handover in Q2 2025 and 99% built in July 2026, 15 months past that date. Off-plan units sell at AED 2.41M (AED 6,699/sqft) over 2 sales in 12 months.

Off-plan price, typical unit

2.41MAED

AED 6,699/sqft · 2 sales in 12 months

Built99%

Started Nov 2016Registered handover Apr 2025 · overdue

DLD project register, Jul 2026

Median off-plan sale
AED 2.41M
Escrow
مصرف ابوظبى الاسلامى

Saves the tower’s record to your account.

Is Ciel a safe off-plan buy?In escrow; 99% built and 15 months past its registered handover; no record of the builder

  1. Is it on schedule?99% built in July 2026, 15 months past its registered April 2025 handover · DLD project register, Jul 202699%Context
  2. Is my money protected?Payments go to an escrow account at مصرف ابوظبى الاسلامى, as registered with the Land DepartmentEscrowContext
  3. Is the price fair?AED 6,699/sqft over 2 off-plan sales; too few sales to compare6,699Context
  4. Is it selling?2 off-plan sales registered in the last 12 months, of 1,019 units; the latest on 25 Jun 20262Context
  5. Who is building it?The register names the master developer, Emaar Properties; the builder is not recordedNo record

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

Check an asking price →How each reading works →

How other Dubai Marina projects are tracking1 of the 3 nearest-to-finished are past their registered dates

ProjectBuilt%Registered date
Cielthis project99%Apr 2025 · past date
Marina Shores87%Dec 2026
PELaGOS By IGO84%Mar 2026 · past date
LIV Lux79%Dec 2026

“Past date”: the registered date has already passed · 4 of 10 live Dubai Marina projects past theirs · DLD register and inspections, October 2026

All 67 Dubai Marina projects →

As registered with the Land DepartmentWhere Ciel is, and who is on its register row

Escrow agent
مصرف ابوظبى الاسلامى
Master developer
Emaar Properties
Registered start
November 2016
Configuration
B+G+11P+70F+R Hotel.The project designed to have a concrete structure and block with internal and external finishes.
Pills show median resale price per sqft, AED. 1 of 1 published tower pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in Ciel

Towers inside this project that have enough registered resales for their own record.

Ask about Ciel

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will Ciel be completed?
The developer registered handover for April 2025; that date has passed with no completion recorded, 15 months on, and the project was 99% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
What does Ciel cost per square foot?
AED 6,699 per sqft, the median of 2 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 2.41M.
Is Ciel in escrow?
Yes: the Land Department register names مصرف ابوظبى الاسلامى as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of Ciel?
The register names the master developer, Emaar Properties, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
How many units does Ciel have?
1,019 registered units. Dubai Land Department project register as of July 2026.

For agents

Send Ciel to a client as a branded report

Create client report

Off-plan record for Ciel

Record type
Project-level off-plan register record
Data date
Evidence base
1,019 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/dubai-marina/ciel
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Ciel, off-plan.” Dubai Marina, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-marina/ciel