Registered for handover in Q2 2025 and 53% built in July 2026, 13 months past that date. Off-plan units sell at AED 997,500 (AED 1,323/sqft), 20% below the Dubai Silicon Oasis off-plan median.
Off-plan price, typical unit
997,500AED
AED 1,323/sqft · 20% below Dubai Silicon Oasis off-plan · 90 sales in 12 months
Started Aug 2022Registered handover Jun 2025 · overdue
DLD project register, Jul 2026
- Median off-plan sale
- AED 997,500
- Titles issued
- 0 of 711
- Escrow
- بنك دبي الاسلامي (شركة مساهمة عامة)
Saves the tower’s record to your account.
Is Tria by Deyaar a safe off-plan buy?In escrow; 53% built and 13 months past its registered handover; no record of the builder
- Is it on schedule?53% built in July 2026, 13 months past its registered June 2025 handover · DLD project register, Jul 202653%Context
- Is my money protected?Payments go to an escrow account at بنك دبي الاسلامي (شركة مساهمة عامة), as registered with the Land DepartmentEscrowContext
- Is the price fair?AED 1,323/sqft, 20.3% below the Dubai Silicon Oasis off-plan median across 13 projects-20.3%Context
- Is it selling?90 off-plan sales registered in the last 12 months, of 711 units; the latest on 12 Oct 202690Context
- Who is building it?The register names the master developer, Dubai Integrated Economic Zones Authority; the builder is not recordedNo record
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built711 units, mostly one-beds and two-beds; none titled yet
DLD unit register · balconies a median 12% of unit area · median off-plan sale AED 997,500
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
711 units in DLD’s register for Tria by Deyaar, floor by floor.
Show 400 of 711 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Dubai Silicon Oasis projects are tracking2 of the 3 nearest-to-finished are past their registered dates
“Past date”: the registered date has already passed · 3 of 11 live Dubai Silicon Oasis projects past theirs · DLD register and inspections, October 2026
All 65 Dubai Silicon Oasis projects →As registered with the Land DepartmentWhere Tria by Deyaar is, and who is on its register row
- Escrow agent
- بنك دبي الاسلامي (شركة مساهمة عامة)
- Master developer
- Dubai Integrated Economic Zones Authority
- Registered start
- August 2022
- Configuration
- G+3P+28 Residential+Commercal.The project designed to have a concrete structure and block with internal and external finishes.
Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in Tria by Deyaar
Towers inside this project that have enough registered resales for their own record.
Ask about Tria by Deyaar
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will Tria by Deyaar be completed?
- The developer registered handover for June 2025; that date has passed with no completion recorded, 13 months on, and the project was 53% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
- What does Tria by Deyaar cost per square foot?
- AED 1,323 per sqft, the median of 90 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 997,500. That is 20.3% below the Dubai Silicon Oasis off-plan median across 13 projects.
- Is Tria by Deyaar in escrow?
- Yes: the Land Department register names بنك دبي الاسلامي (شركة مساهمة عامة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of Tria by Deyaar?
- The register names the master developer, Dubai Integrated Economic Zones Authority, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
- How many units does Tria by Deyaar have?
- 711 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send Tria by Deyaar to a client as a branded report
Off-plan record for Tria by Deyaar
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 711 registered units; DLD project register as of 2026-07-06
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record
- /off-plan/apartments/dubai/dubai-silicon-oasis/tria-by-deyaar
Cite as: Dubai Wealth Index. “Tria by Deyaar, off-plan.” Dubai Silicon Oasis, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-silicon-oasis/tria-by-deyaar