Urban Park Residences
Registered for handover in Q2 2026 and 68% built in July 2026, 3 months past that date. Off-plan units sell at AED 1.04M (AED 1,531/sqft), 5% above the Dubai Sports City off-plan median.
Off-plan price, typical unit
1.04MAED
AED 1,531/sqft · 5% above Dubai Sports City off-plan · 59 sales in 12 months
Started Oct 2024Registered handover Apr 2026 · overdue
DLD inspection, 6 Jul 2026
- Median off-plan sale
- AED 1.04M
- Titles issued
- 0 of 187
- Escrow
- يونايتد بنك ليمتد (مكتب ادارة)
Saves the tower’s record to your account.
Is Urban Park Residences a safe off-plan buy?In escrow; 68% built and 3 months past its registered handover
- Is it on schedule?68% built in July 2026, 3 months past its registered April 2026 handover · DLD inspection, 6 Jul 202668%Context
- Is my money protected?Payments go to an escrow account at يونايتد بنك ليمتد (مكتب ادارة), as registered with the Land DepartmentEscrowContext
- Is the price fair?AED 1,531/sqft, 4.6% above the Dubai Sports City off-plan median across 24 projects+4.6%Context
- Is it selling?59 off-plan sales registered in the last 12 months, of 187 units; the latest on 5 Oct 202659Context
- Who is building it?Urban Venture, licence no. 1947Context
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built187 units, mostly one-beds and two-beds; none titled yet
DLD unit register · balconies a median 17% of unit area · median off-plan sale AED 1.04M
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
187 units in DLD’s register for Urban Park Residences, floor by floor.
Show 187 of 187 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Dubai Sports City projects are trackingThe nearest-to-finished are all past their registered dates
“Past date”: the registered date has already passed · 6 of 17 live Dubai Sports City projects past theirs · DLD register and inspections, October 2026
All 74 Dubai Sports City projects →As registered with the Land DepartmentWhere Urban Park Residences is, and who is on its register row
- Escrow agent
- يونايتد بنك ليمتد (مكتب ادارة)
- Developer, as licensed
- URBAN VENTURE REAL ESTATE DEVELOPMENT L.L.C (no. 1947)
- Master developer
- Dubai Sports City
- Registered start
- October 2024
- Configuration
- 2B+G+15+R
Construction progress is DLD’s inspection of 6 Jul 2026. DLD’s published project register still lags it, so the later inspection is used and dated on its own. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in Urban Park Residences
Towers inside this project that have enough registered resales for their own record.
Ask about Urban Park Residences
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will Urban Park Residences be completed?
- The developer registered handover for April 2026; that date has passed with no completion recorded, 3 months on, and the project was 68% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department inspection of 6 Jul 2026.
- What does Urban Park Residences cost per square foot?
- AED 1,531 per sqft, the median of 59 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 1.04M. That is 4.6% above the Dubai Sports City off-plan median across 24 projects.
- Is Urban Park Residences in escrow?
- Yes: the Land Department register names يونايتد بنك ليمتد (مكتب ادارة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of Urban Park Residences?
- URBAN VENTURE REAL ESTATE DEVELOPMENT L.L.C, licence no. 1947, by the register’s own licence number; the master developer that owns the land is Dubai Sports City. Dubai Land Department project register as of July 2026.
- How many units does Urban Park Residences have?
- 187 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send Urban Park Residences to a client as a branded report
Off-plan record for Urban Park Residences
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 187 registered units; DLD project register as of 2026-07-06; construction state from the DLD inspection, 6 Jul 2026
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
Cite as: Dubai Wealth Index. “Urban Park Residences, off-plan.” Dubai Sports City, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-sports-city/urban-park-residences