The V Tower
Recorded complete in September 2023.
Started Jan 2020Completed Sept 2023
DLD project register, Jul 2026
- Titles issued
- 369 of 369
- Escrow
- بنك ابوظبى التجارى
Saves the tower’s record to your account.
Is The V Tower a safe off-plan buy?Recorded complete in September 2023
- Is it on schedule?Recorded complete in September 2023, on its registered date to the day: the register often stamps one onto the other · DLD project register, Jul 2026100%Context
- Is my money protected?The register named the escrow agent: بنك ابوظبى التجارىEscrowContext
- Is the price fair?No off-plan sale registered in 12 months to price it onNo record
- Is it selling?No off-plan sale registered in 12 months; the last in March 20240Context
- Who is building it?Tiger Properties, licence no. 581; 1 of its 6 dated live projects are past their registered dates17%Context
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built369 units, mostly one-beds and studios; all titled
DLD unit register · balconies a median 17% of unit area
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
369 units in DLD’s register for The V Tower, floor by floor.
Show 369 of 369 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Dubailand Residence Complex projects are tracking2 of the 3 nearest-to-finished are past their registered dates
“Past date”: the registered date has already passed · 5 of 65 live Dubailand Residence Complex projects past theirs · DLD register and inspections, October 2026
All 85 Dubailand Residence Complex projects →As registered with the Land DepartmentWhere The V Tower is, and who is on its register row
- Escrow agent
- بنك ابوظبى التجارى
- Developer, as licensed
- TIGER PROPERTIES (no. 581)
- Master developer
- Dubailand Residences
- Registered start
- January 2020
- Configuration
- PROJECT CONSISTS OF 3B+G+17+R RESIDENTIAL BUILDING LOCATED IN WADI AL SAFA 5. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES
Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in The V Tower
Towers inside this project that have enough registered resales for their own record.
More from Tiger Properties
Live projects registered to the same developer, most advanced first.
Altai Tower
Jumeirah Village Triangle · registered handover Jan 2026
98%
built, DLD register
Volga Tower
Jumeirah Village Triangle · no registered handover date
18%
built, DLD register
Red Square
Jumeirah Village Triangle · no registered handover date
9%
built, DLD register
Tiger Sky Tower
Business Bay · no registered handover date
7%
built, DLD register
Ask about The V Tower
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will The V Tower be completed?
- The register records The V Tower complete in September 2023. Dubai Land Department project register as of July 2026.
- Is The V Tower in escrow?
- Yes: the Land Department register names بنك ابوظبى التجارى as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of The V Tower?
- TIGER PROPERTIES, licence no. 581, by the register’s own licence number; the master developer that owns the land is Dubailand Residences. Dubai Land Department project register as of July 2026.
- How many units does The V Tower have?
- 369 registered units, of which 369 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send The V Tower to a client as a branded report
Off-plan record for The V Tower
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 369 registered units; DLD project register as of 2026-07-06
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions