Tiger Properties, delivery record

Registered projects
26
DLD register, Jul 2026
Live past their registered date
55%
6 of 11 live projects with dates · 3 without dates
Median slippage
1 measurable completion
Completed
12
11 dated to the registered day

Every project the Dubai Land Department registers to Tiger Properties, matched by the developer licence number on each registration — a high-confidence identity. A live project past the completion date the developer itself registered is counted as overdue, not as late: it has not been delivered yet, and this site does not forecast when it will be.

The register dates 11 of this developer’s 12 completed projects to the registered day exactly — it writes the completion date onto the planned one — so those show no slippage in either direction and are excluded from the figure above rather than counted as delivered on time. That leaves 1 measurable completion, too few to publish a median.

Live projects

14 registered and not yet recorded complete, most advanced first.

Delivered projects

12 recorded complete, most recent first. Slippage is months from the registered date to the recorded one; negative is early.

ProjectLocalityRegisteredCompletedSlippage, months
NoblesBusiness BayAug 2024Aug 2024on time
The V TowerDubailand Residence ComplexSept 2023Sept 2023on time
Blue WaveDubailand Residence ComplexJan 2023Jan 2023on time
ReginaJumeirah Village CircleMay 2022Mar 2022-2
O 2Jumeirah Village CircleJun 2021Jun 2021on time
The SquareJumeirah Village CircleDec 2020Dec 2020on time
Al Jawhara TowerJumeirah Village TriangleMar 2020Mar 2020on time
SamayaMajanJul 2019Jul 2019on time
Al Manarah TowerJumeirah Village TriangleNov 2017Nov 2017on time
Dana TowerJumeirah Village CircleDec 2013Dec 2013on time
Marina PinnacleDubai MarinaJul 2011Jul 2011on time
Lake City TowerJumeirah Lake TowersSept 2008Sept 2008on time

Tiger Properties, delivery record

Record type
Developer-level off-plan register record
Data date
Evidence base
26 registered projects, 14 live of which 6 past their registered date, 1 completions with a measurable slippage of 12 completed; DLD project register as of 2026-07-06; identity high-confidence over 1 licensed company
Sources
Dubai Land Department project register
Canonical record
/developers/tiger-properties
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Tiger Properties, delivery record.” Register to 2026-07-06, data to 2026-09-11. https://dubaiwealthindex.com/developers/tiger-properties