Under construction · 93 units · started Jan 2024 · International City Phase 2

Registered for handover in Q3 2025 and 50% built in July 2026, 11 months past that date. Off-plan units sell at AED 460,798 (AED 1,317/sqft), 10% above the International City Phase 2 off-plan median.

Off-plan price, typical unit

460,798AED

AED 1,317/sqft · 10% above International City Phase 2 off-plan · 17 sales in 12 months

Built50%

Started Jan 2024Registered handover Aug 2025 · overdue

DLD project register, Jul 2026

Median off-plan sale
AED 460,798
Titles issued
0 of 93
Escrow
بنك المشرق (شركة مساهمة عامة)

Saves the tower’s record to your account.

Is MOONSA Residences a safe off-plan buy?In escrow; 50% built and 11 months past its registered handover

  1. Is it on schedule?50% built in July 2026, 11 months past its registered August 2025 handover · DLD project register, Jul 202650%Context
  2. Is my money protected?Payments go to an escrow account at بنك المشرق (شركة مساهمة عامة), as registered with the Land DepartmentEscrowContext
  3. Is the price fair?AED 1,317/sqft, 9.8% above the International City Phase 2 off-plan median across 31 projects+9.8%Context
  4. Is it selling?17 off-plan sales registered in the last 12 months, of 93 units; the latest on 23 Sept 202617Context
  5. Who is building it?Dugasta, licence no. 1157Context

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

Check an asking price →How each reading works →

What is being built93 units, mostly studios and one-beds; none titled yet

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
Studio40349–6090
1 bed25840–9300
2 bed24828–9510
3 bed42,165–2,1670

DLD unit register · balconies a median 16% of unit area · median off-plan sale AED 460,798

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

93 units in DLD’s register for MOONSA Residences, floor by floor.

Show 93 of 93 units
FloorUnitTypeSqftBalconyTitle issued
11 · 1011 bed77656Not yet
11 · 1021 bed77656Not yet
11 · 1032 bed765—Not yet
11 · 104Studio285—Not yet
11 · 105Studio35759Not yet
11 · 106Studio287—Not yet
11 · 1072 bed1,004240Not yet
11 · 1081 bed990269Not yet
11 · 109Studio656217Not yet
11 · 1102 bed1,8701,106Not yet

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other International City Phase 2 projects are tracking2 of the 3 nearest-to-finished are past their registered dates

ProjectBuilt%Registered date
Mayflower Residences96%Mar 2026 · past date
08 Life Residences65%May 2026 · past date
Tavora Residences by Jhk Heights Real Estate Development61%Dec 2026
MOONSA Residencesthis project50%Aug 2025 · past date

“Past date”: the registered date has already passed · 6 of 20 live International City Phase 2 projects past theirs · DLD register and inspections, October 2026

All 36 International City Phase 2 projects →

As registered with the Land DepartmentWhere MOONSA Residences is, and who is on its register row

Escrow agent
بنك المشرق (شركة مساهمة عامة)
Developer, as licensed
DUGASTA PROPERTIES DEVELOPMENT L.L.C (no. 1157)
Master developer
International City LLC
Registered start
January 2024
Configuration
B + G + 1 + 2-6 Typ +7 + Roof Residential Building.The project designed to have a concrete structure and block with internal and external finishes.
Pills show median resale price per sqft, AED. 1 of 1 published tower pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in MOONSA Residences

Towers inside this project that have enough registered resales for their own record.

Ask about MOONSA Residences

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will MOONSA Residences be completed?
The developer registered handover for August 2025; that date has passed with no completion recorded, 11 months on, and the project was 50% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
What does MOONSA Residences cost per square foot?
AED 1,317 per sqft, the median of 17 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 460,798. That is 9.8% above the International City Phase 2 off-plan median across 31 projects.
Is MOONSA Residences in escrow?
Yes: the Land Department register names بنك المشرق (شركة مساهمة عامة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of MOONSA Residences?
DUGASTA PROPERTIES DEVELOPMENT L.L.C, licence no. 1157, by the register’s own licence number; the master developer that owns the land is International City LLC. Dubai Land Department project register as of July 2026.
How many units does MOONSA Residences have?
93 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send MOONSA Residences to a client as a branded report

Create client report

Off-plan record for MOONSA Residences

Record type
Project-level off-plan register record
Data date
Evidence base
93 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/international-city-phase-2/moonsa-residences
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “MOONSA Residences, off-plan.” International City Phase 2, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/international-city-phase-2/moonsa-residences