Off-plan · DLD project register as of 6 Jul 2026

Uh East by Ellington

Under construction · 377 units · started May 2023 · Jumeirah Lake Towers

Registered for handover in Q1 2026 and 47% built in June 2026, 3 months past that date. Off-plan units sell at AED 1.76M (AED 1,905/sqft), 35% below the Jumeirah Lake Towers off-plan median.

Off-plan price, typical unit

1.76MAED

AED 1,905/sqft · 35% below Jumeirah Lake Towers off-plan · 57 sales in 12 months

Built47%

Started May 2023Registered handover Mar 2026 · overdue

DLD inspection, 1 Jun 2026 · no later inspection

Median off-plan sale
AED 1.76M
Titles issued
0 of 377
Escrow
بنك الإمارات دبي الوطني (ش.م.ع)

Saves the tower’s record to your account.

Is Uh East by Ellington a safe off-plan buy?In escrow; 47% built and 3 months past its registered handover

  1. Is it on schedule?47% built in June 2026, 3 months past its registered March 2026 handover; DLD has published no later inspection of it · DLD inspection, 1 Jun 202647%Context
  2. Is my money protected?Payments go to an escrow account at بنك الإمارات دبي الوطني (ش.م.ع), as registered with the Land DepartmentEscrowContext
  3. Is the price fair?AED 1,905/sqft, 35.2% below the Jumeirah Lake Towers off-plan median across 19 projects-35.2%Context
  4. Is it selling?57 off-plan sales registered in the last 12 months, of 377 units; the latest on 17 Sept 202657Context
  5. Who is building it?Ellington Properties, licence no. 1117; 3 of its 13 dated live projects are past their registered dates23%Context

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

Check an asking price →How each reading works →

What is being built377 units, mostly one-beds; none titled yet

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
Studio34407–4470
1 bed215839–9510
2 bed1141,205–1,4500
3 bed141,871–1,8780

DLD unit register · balconies a median 10% of unit area · median off-plan sale AED 1.76M

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

377 units in DLD’s register for Uh East by Ellington, floor by floor.

Show 377 of 377 units
FloorUnitTypeSqftBalconyTitle issued
T11 · E-6011 bed90471Not yet
T11 · E-6021 bed92679Not yet
T11 · E-6031 bed84076Not yet
T11 · E-6041 bed84871Not yet
T11 · E-605Studio44747Not yet
T11 · E-6062 bed1,331159Not yet
T11 · E-6071 bed95390Not yet
T11 · E-6081 bed96997Not yet
P21 · E-2011 bed90268Not yet
P21 · E-2021 bed1,048204Not yet

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Jumeirah Lake Towers projects are trackingThe nearest-to-finished are all past their registered dates

ProjectBuilt%Registered date
Me Do Re 295%Dec 2025 · past date
The Wind Tower II85%Jun 2023 · past date
The Wind Tower I75%Jun 2023 · past date
Uh East by Ellingtonthis project47%Mar 2026 · past date

“Past date”: the registered date has already passed · 8 of 15 live Jumeirah Lake Towers projects past theirs · DLD register and inspections, October 2026

All 48 Jumeirah Lake Towers projects →

As registered with the Land DepartmentWhere Uh East by Ellington is, and who is on its register row

Escrow agent
بنك الإمارات دبي الوطني (ش.م.ع)
Developer, as licensed
ELLINGTON PROPERTIES DEVELOPMENT L.L.C (no. 1117)
Master developer
DMCC
Registered start
May 2023
Configuration
3B+G+36F+1R Residential+Commercal.The project designed to have a concrete structure and block with internal and external finishes.
Pinned by Google from the registered name; verify the plot before relying on it.Open in Google Maps

Construction progress is DLD’s inspection of 1 Jun 2026. DLD’s published project register still lags it, so the later inspection is used and dated on its own. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in Uh East by Ellington

Towers inside this project that have enough registered resales for their own record.

More from Ellington Properties

Live projects registered to the same developer, most advanced first.

Ask about Uh East by Ellington

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will Uh East by Ellington be completed?
The developer registered handover for March 2026; that date has passed with no completion recorded, 3 months on, and the project was 47% built as of June 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department inspection of 1 Jun 2026.
What does Uh East by Ellington cost per square foot?
AED 1,905 per sqft, the median of 57 registered off-plan sales in the 12 months to 12 Oct 2026; the median unit sold for AED 1.76M. That is 35.2% below the Jumeirah Lake Towers off-plan median across 19 projects.
Is Uh East by Ellington in escrow?
Yes: the Land Department register names بنك الإمارات دبي الوطني (ش.م.ع) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of Uh East by Ellington?
ELLINGTON PROPERTIES DEVELOPMENT L.L.C, licence no. 1117, by the register’s own licence number; the master developer that owns the land is DMCC. Dubai Land Department project register as of July 2026.
How many units does Uh East by Ellington have?
377 registered units, of which 0 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send Uh East by Ellington to a client as a branded report

Create client report

Off-plan record for Uh East by Ellington

Record type
Project-level off-plan register record
Data date
Evidence base
377 registered units; DLD project register as of 2026-07-06; construction state from the DLD inspection, 1 Jun 2026
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/jumeirah-lake-towers/uh-east-by-ellington
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Uh East by Ellington, off-plan.” Jumeirah Lake Towers, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/jumeirah-lake-towers/uh-east-by-ellington