Flamingo Lux Residence, off-plan

Edition DWI-PROJECT-FLAMINGO-LUX-RESIDENCE
Construction
47%
DLD register, July 2026
Planned handover
May 2025
14 months past plan
Titles issued
100%
50 of 50
Off-plan price

Registered to Meydan Group — see every project on its delivery record.

Construction progress is the percentage DLD inspected and recorded in its project register as of July 2026. The register publishes about two months behind sale records, so this figure is older than the sales data on this site, and it is dated separately for that reason. The developer registered handover for May 2025; as of the register date it had not been recorded complete, 14 months on. That is a fact about the past, not a prediction of when it will finish.

Unit mix

From the title register. A unit counts as registered once DLD has issued its title, which for an off-plan project happens at handover — so a live project shows few or none regardless of how many units the developer has sold. The unregistered remainder is not the same as being for sale. Balcony area is a median 15.15% of unit area across the units that register both.

TypeUnitsTitles issuedSize, sqft
1 bed1111100%695–846
2 bed2121100%1,095–1,670
3 bed1818100%1,829–2,800

Sizes are the 10th to 90th percentile of registered floor area, not the extremes: one mislabelled unit would otherwise set the range.

Published buildings in Flamingo Lux Residence

Towers inside this project that have enough registered resales for their own record.

As registered

Escrow agent
بنك أبوظبي الأول ش.م.ع.
Developer, as registered
مجموعة ميدان (ش.ذ.م.م)
Registered start
September 2023
Configuration
Mixed-Use Residential Building (G+4F+R).The project designed to have a concrete structure and block with internal and external finishes.

The developer name is held in Arabic in the register and shown as recorded. Off-plan price is the median of registered off-plan sales across this project's published buildings, 24 months to 2026-08-26.

Off-plan record for Flamingo Lux Residence

Record type
Project-level off-plan register record
Data date
Evidence base
50 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/meydan/flamingo-lux-residence
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Flamingo Lux Residence, off-plan.” Meydan, Dubai. Register to 2026-07-06, data to 2026-08-26. https://dubaiwealthindex.com/off-plan/apartments/dubai/meydan/flamingo-lux-residence.