International City Phase 2 upcoming supply
Every pending apartment project in International City Phase 2, by when it is due, set against the homes let there today. Prices and yields in International City Phase 2 · Off-plan launches
- Data to
- Pending projects
- 20
- Pending units
- 2,101
International City Phase 2: 1,581 apartments planned for 2026–2028, 16% of the homes let there today
Counted against today, 2026-10-18. Register to 2026-07-06; leases to 2026-10-12.
- Planned 2026–28
- 1,581
- 2,101 pending in all
- Homes let today
- 9,675
- Ejari tenancies in force
- Planned ÷ homes let
- 16%
- 0.2× a year of leasing
- Due in 12 months
- 1,072
- 639 already past their date
When it is due
Every pending apartment, by its registered completion quarter.
Handover calendar
Apartment units, by planned completion quarter
- Late: 639639
- Q4 ’26: 307307
- Q1 ’27: 393393
- Q2 ’27: 218218
- Q3 ’27: 3030
- Q4 ’27: 124124
- Q1 ’28: 264264
- Q2 ’28: 00
- Q3 ’28: 00
- Q4 ’28: 126126
Which homes, against which lets
Planned for 2026–2028 by bedroom type, against the homes of that type let today.
Planned apartments
Units due 2026–2028, by bedroom type
- Studio647
- 1 bed762
- 2 bed136
- 3 bed33
- 4+ bed3
Planned as a share of homes let today
Planned units ÷ registered tenancies in force
- Studio23%
- 1 bed13%
- 2 bed12%
Project calendar
20 pending projects, 2,101 units. Progress is the register's reported share built.
Planned date passed639 units · 7 projects
- MOONSA Residences2025-08-259350%
- Equiti Tower2025-08-308833%
- The Maiden Residence2025-12-317124%
- Mayflower Residences2026-03-319796%
- Linden Residences2026-03-31720%
- 08 Life Residences2026-05-319965%
- Stellar Axis by Ajmal Estate Developers2026-10-0111927%
2026 Q4307 units · 3 projects
- Tavora Residences by Jhk Heights Real Estate Development2026-12-159561%
- Moonsa Residences 22026-12-311251%
- Vio Residences2026-12-31876%
2027 Q1393 units · 4 projects
- Sports View Residence 2 by Al Helal Al Zahaby2027-01-311280%
- 27 East End Garden Residences By Mirha Homes Real Estate Development2027-01-31962%
- Kyomi Residence2027-02-011200%
- Zyra Vista Residences2027-03-31490%
2027 Q2218 units · 2 projects
- Nest2027-04-011120%
- Elevia Residences2027-06-301060%
2027 Q330 units · 1 project
- Sunlight Homes2027-09-30300%
2027 Q4124 units · 1 project
- Ventana Residences2027-10-011247%
2028 Q1264 units · 1 project
- Zenith Residences2028-03-012643%
2028 Q4126 units · 1 project
- Chapter 01 By Newbury Developments2028-10-011260%
Method and limits
Planned supply is every apartment unit in a project the Land Department register lists as neither complete nor cancelled, placed by its registered completion date and counted against today. Homes let today are the registered Ejari tenancies in force on the data date. A planned date is the developer's, not a delivery forecast; completions slip, and some homes are owner-occupied or let short-term.
Why tenancies and not the register: the unit register only reaches back to recently registered projects, so it misses most of the homes standing today. Ejari records every registered lease with its start and end. Full methodology
International City Phase 2 upcoming apartment supply
- Record type
- Planned supply against tenancies
- Data date
- Evidence base
- 2,101 pending apartment units in 20 projects; 9,675 tenancies in force
- Sources
- Dubai Land Department project and unit registers; Ejari tenancies
- Canonical record
- /supply/apartments/dubai/international-city-phase-2
Cite as: Dubai Wealth Index. “International City Phase 2 upcoming apartment supply.” International City Phase 2, Dubai. Data to 2026-10-12. https://dubaiwealthindex.com/supply/apartments/dubai/international-city-phase-2