Dubai Holding Asset Management, delivery record
- Edition DWI-DEVELOPER-DUBAI-HOLDING-ASSET-MANAGEMENT
- Registered projects
- 51
- DLD register, Jul 2026
- Delivered on time
- 50%
- of 2 completed
- Median slippage
- 0.5months
- registered date to recorded completion
- Live and overdue
- 7
- of 49 live
Every project the Dubai Land Department registers to دى اتش ايه ام منطقه حره - ذ.م.م, which this site publishes as Dubai Holding Asset Management — a medium-confidence reading of the registered Arabic name. On-time delivery and slippage are measured on completed projects against the completion date the developer itself registered. A live project past that date is counted as overdue, not as late: it has not been delivered yet, and this site does not forecast when it will be.
Live projects
49 registered and not yet recorded complete, most advanced first.
Delivered projects
2 recorded complete, most recent first. Slippage is months from the registered date to the recorded one; negative is early.
Dubai Holding Asset Management, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 51 registered projects, 2 completed; DLD project register as of 2026-07-06; identity medium-confidence
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/dubai-holding-asset-management
Cite as: Dubai Wealth Index. “Dubai Holding Asset Management, delivery record.” Register to 2026-07-06, data to 2026-08-26. https://dubaiwealthindex.com/developers/dubai-holding-asset-management.