Maritime City
25 registered projects · 23 live, 10,693 units · launches 2015–2025
1 of Maritime City’s 17 dated live projects (6%) is past its registered completion date. The median live project is 4% built, and 3 more are due within 12 months.
Live projects past their registered date
6%
- Past date
- 1 of 17 dated
- Median built, live projects
- 4%
- Due within 12 months
- 3
- Units not yet titled
- 10,693
Leaders
- Most advanced
- Aria By Beyond· 85%
- Latest handover
- Riva Residence· Feb 2026
Launch vs resale, development by development-25.0% from launch to resale across Maritime City: AED 2,758 a sqft at launch, 2,068 on resale
Survivors only, unpaired, before costs: the all-time median off-plan price per sq ft against ready resales in the 12 months to 12 Oct 2026, pooled across each development’s towers. A median needs 3 sales. Register: construction as the DLD register or a later inspection records it; “past date” means its registered completion month has passed, register Jul 2026. · Showing 20 of 26 rows
Handover calendar, by registered completion quarterMaritime City: 4,422 apartments planned for 2026–2028, 273% of the homes let there today
Handover calendar
Apartment units, by planned completion quarter
- Late: 191191
- Q4 ’26: 858858
- Q1 ’27: 00
- Q2 ’27: 294294
- Q3 ’27: 00
- Q4 ’27: 898898
- Q1 ’28: 00
- Q2 ’28: 354354
- Q3 ’28: 1.3k1,250
- Q4 ’28: 768768
- 2029 +: 3.5k3,454
- No date: 2.6k2,626
A planned date is the developer’s, not a delivery forecast
Maritime City supply by year →Every project in Maritime City25 off-plan projects, A to Z
25 projects
A
- Aria By Beyondpast date85% built
B
- Breez by Danube0% built
C
- Chelsea Residences 2 by DAMAC0% built
- Chelsea Residences by DAMAC0% built
- Coral Reefno date13% built
F
- Franck Muller Yachting0% built
H
- Harbour Lights26% built
I
- IL Vento0% built
K
- Kanyon By Beyond0% built
L
- LIV Maritime4% built
M
- Mar Casa56% built
N
- Nautica Oneno date32% built
- Nautica Twono date32% built
O
- Oceanz 1 By Danubeno date13% built
- Oceanz 2 By Danubeno date10% built
- Oceanz 3 By Danubeno date7% built
- Orise1% built
R
- Riva Residencecomplete
S
- Saria6% built
- Sensia0% built
- Soulever' By Beyond0% built
T
- Talea0% built
- The Anwa by Omniyatcomplete
- The Mural0% built
- The Pier35% built
Construction progress as the DLD register or a later inspection records it · “past date”: live, and its registered completion month has passed · “no date”: the register gives none
Back to top ↑Off-plan apartment record for Maritime City
- Record type
- Area-level off-plan delivery record
- Data date
- Evidence base
- 25 registered projects, 23 live; 2 buildings with launch and resale evidence
- Sources
- Dubai Land Department project register and sale transactions
- Canonical record
- /off-plan/apartments/dubai/dubai-maritime-city
Cite as: Dubai Wealth Index. “Off-plan apartments in Maritime City.” Project register to 2026-07-06, sales to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-maritime-city
Source: Dubai Land Department project register () and sale transactions (to ).