La Vista 03

Completed 2015 · 128 units · started May 2008 · Dubai Silicon Oasis

Recorded complete in April 2015.

Built100%

Started May 2008Completed Apr 2015

DLD project register, Jul 2026

Titles issued
128 of 128
Escrow
مصرف الامارات الاسلامي مساهمة عامة

Saves the tower’s record to your account.

Is La Vista 03 a safe off-plan buy?Recorded complete in April 2015; no record of the builder

  1. Is it on schedule?Recorded complete in April 2015, on its registered date to the day: the register often stamps one onto the other · DLD project register, Jul 2026100%Context
  2. Is my money protected?The register named the escrow agent: مصرف الامارات الاسلامي مساهمة عامةEscrowContext
  3. Is the price fair?No off-plan sale registered in 12 months to price it onNo record
  4. Is it selling?No off-plan sale registered in 12 months; the last in July 20170Context
  5. Who is building it?The register names the master developer, Dubai Integrated Economic Zones Authority; the builder is not recordedNo record

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

Check an asking price →How each reading works →

What is being built128 units, mostly one-beds; all titled

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
1 bed116683–933116
2 bed12942–94212

DLD unit register · balconies a median 9% of unit area

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

128 units in DLD’s register for La Vista 03, floor by floor.

Show 128 of 128 units
FloorUnitTypeSqftBalconyTitle issued
1LA VISTA 3 · 1011 bed848114Yes
1LA VISTA 3 · 1021 bed931108Yes
1LA VISTA 3 · 1031 bed932108Yes
1LA VISTA 3 · 1041 bed74658Yes
1LA VISTA 3 · 1051 bed74458Yes
1LA VISTA 3 · 1061 bed933109Yes
1LA VISTA 3 · 1071 bed933109Yes
1LA VISTA 3 · 1081 bed828114Yes
1LA VISTA 3 · 1091 bed69853Yes
1LA VISTA 3 · 1101 bed68753Yes

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Dubai Silicon Oasis projects are trackingThe nearest-to-finished are all past their registered dates

ProjectBuilt%Registered date
Tria by Deyaar53%Jun 2025 · past date
Oasis Loft50%Sept 2026 · past date
Aura Elite44%Apr 2026 · past date

“Past date”: the registered date has already passed · 3 of 11 live Dubai Silicon Oasis projects past theirs · DLD register and inspections, October 2026

All 65 Dubai Silicon Oasis projects →

As registered with the Land DepartmentWhere La Vista 03 is, and who is on its register row

Escrow agent
مصرف الامارات الاسلامي مساهمة عامة
Master developer
Dubai Integrated Economic Zones Authority
Registered start
May 2008
Configuration
Freehold residential building located in Dubai Silicon Oasis, designed to have G+8 floors. The building is being constructed as a concrete structure with internal and external finishes.
Pills show median resale price per sqft, AED. 1 of 1 published tower pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in La Vista 03

Towers inside this project that have enough registered resales for their own record.

Ask about La Vista 03

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will La Vista 03 be completed?
The register records La Vista 03 complete in April 2015. Dubai Land Department project register as of July 2026.
Is La Vista 03 in escrow?
Yes: the Land Department register names مصرف الامارات الاسلامي مساهمة عامة as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of La Vista 03?
The register names the master developer, Dubai Integrated Economic Zones Authority, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
How many units does La Vista 03 have?
128 registered units, of which 128 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send La Vista 03 to a client as a branded report

Create client report

Off-plan record for La Vista 03

Record type
Project-level off-plan register record
Data date
Evidence base
128 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/dubai-silicon-oasis/la-vista-03
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “La Vista 03, off-plan.” Dubai Silicon Oasis, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/dubai-silicon-oasis/la-vista-03