Sobha Hartland Greens Phase II

Completed 2020 · 341 units · started Sept 2016 · Sobha Hartland

Recorded complete in January 2020.

Built100%

Started Sept 2016Completed Jan 2020

DLD project register, Jul 2026

Titles issued
341 of 341
Escrow
مصرف ابوظبى الاسلامى

Is Sobha Hartland Greens Phase II a safe off-plan buy?Recorded complete in January 2020

  1. Is it on schedule?Recorded complete in January 2020, on its registered date to the day: the register often stamps one onto the other · DLD project register, Jul 2026100%Context
  2. Is my money protected?The register named the escrow agent: مصرف ابوظبى الاسلامىEscrowContext
  3. Is the price fair?No off-plan sale registered in 12 months to price it onNo record
  4. Is it selling?No off-plan sale registered in 12 months; the last in October 20200Context
  5. Who is building it?Sobha, licence no. 966; 0 of its 10 dated live projects are past their registered dates0%Context

A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026

How each reading works →

What is being built341 units, mostly one-beds; all titled

TypeShare of the buildingUnitsSize, sqft (p10–p90)Titled
Studio46531–59546
1 bed213859–866213
2 bed441,303–2,02644
3 bed361,894–3,10836
4+ bed24,059–4,2012

DLD unit register · balconies a median 7% of unit area

Every unit, floor by floor →

Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.

Every unit, as registered

341 units in DLD’s register for Sobha Hartland Greens Phase II, floor by floor.

Show 341 of 341 units
FloorUnitTypeSqftBalconyTitle issued
13 · 21011 bed86358Yes
13 · 21021 bed86158Yes
13 · 2104Studio551—Yes
13 · 21081 bed800—Yes
13 · 2109Studio532—Yes
13 · 21111 bed86559Yes
13 · 21121 bed86759Yes
13 · 21133 bed1,901190Yes
13 · 21141 bed86259Yes
13 · 21151 bed86459Yes

A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.

How other Sobha Hartland projects are trackingThe nearest-to-finished are all within their registered dates

ProjectBuilt%Registered date
Sobha Creek Vistas Heights43%—
The Highbury37%—

“Past date”: the registered date has already passed · DLD register and inspections, October 2026

All 20 Sobha Hartland projects →

As registered with the Land DepartmentWhere Sobha Hartland Greens Phase II is, and who is on its register row

Escrow agent
مصرف ابوظبى الاسلامى
Developer, as licensed
SOBHA L.L.C (no. 966)
Master developer
Sobha
Registered start
September 2016
Configuration
SITUATED AT THE CENTER OF SOBHA HARTLAND IS (SOBHA HARTLAND GREENS PHASE II) THE BUILDINGS x 2 with common basement+G+8+R AND CONSISTS OF STUDIOS, ONE, TWO AND THREE BEDROOM APARTMENTS AND RETAIL SHOP BUILDING CONSIST OF CONCRETE STRUCTURE WITH INTERNAL AND EXTERNAL FINISHES.
Pills show median resale price per sqft, AED. 1 of 2 published towers pinned; verify a plot before relying on it.Open in Apple Maps

Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .

Published buildings in Sobha Hartland Greens Phase II

Towers inside this project that have enough registered resales for their own record.

More from Sobha

Live projects registered to the same developer, most advanced first.

Ask about Sobha Hartland Greens Phase II

Looking to buy or rent here? Tell us what you need: unit type, budget, timing.

We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.

A phone or an email is enough.

By pressing Request info, you agree that DWI and the licensed real-estate agents it works with may contact you about this enquiry.

Common questions

When will Sobha Hartland Greens Phase II be completed?
The register records Sobha Hartland Greens Phase II complete in January 2020. Dubai Land Department project register as of July 2026.
Is Sobha Hartland Greens Phase II in escrow?
Yes: the Land Department register names مصرف ابوظبى الاسلامى as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
Who is the developer of Sobha Hartland Greens Phase II?
SOBHA L.L.C, licence no. 966, by the register’s own licence number; the master developer that owns the land is Sobha. Dubai Land Department project register as of July 2026.
How many units does Sobha Hartland Greens Phase II have?
341 registered units, of which 341 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.

For agents

Send Sobha Hartland Greens Phase II to a client as a branded report

Create client report

Off-plan record for Sobha Hartland Greens Phase II

Record type
Project-level off-plan register record
Data date
Evidence base
341 registered units; DLD project register as of 2026-07-06
Sources
Dubai Land Department project register, construction inspections and title register; sale transactions
Canonical record
/off-plan/apartments/dubai/sobha-hartland/sobha-hartland-greens-phase-ii
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Sobha Hartland Greens Phase II, off-plan.” Sobha Hartland, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/sobha-hartland/sobha-hartland-greens-phase-ii