Sobha logoDelivery record · DLD project register as of 06 Jul 2026

Sobha

32 registered projects · 14 completed · 18 live · 4th of 22 developers on delivery

None of Sobha’s 10 dated live projects is past the completion date it registered itself: 0%, against 13% across the 28 Dubai developers with ten or more registered projects. Its most-traded tower, Skyvue Altier, registered 431 sales in the last 12 months at a median AED 2.19M (AED 3,010/sqft).

Live projects past their registered date

0%0 of 10

28 developers with ten or more projects: 13%

Object One 0%Sobha 0%Dubai 13%
Registered projects
32
Completed
14
Live, no registered date
8

Does Sobha deliver on time?No dated live project is past its own registered date; its most-traded tower sells at a typical AED 2.19M (AED 3,010/sqft)

  1. Are live projects on time?0 of 10 dated live projects are past the date Sobha registered; 8 more carry no date0%Context
  2. How does it rank?4th of the 22 developers ranked on delivery, fewest overdue first; Dubai’s share past date is 13%4thContext
  3. How late, typically?Median 1 month early over 6 completions with a date distinct from the plan; 8 more were stamped with it−1 moContext
  4. Do its towers trade?Skyvue Altier trades at AED 3,010/sqft on 431 sales, off-plan and ready, in 12 months; 60 or more of its towers have a sale recordAED 2.19MContext

Ranked on the share of live projects past their own registered date · fewest first · register Jul 2026

All 28 developers →

Live projects, most advanced first18 live projects, none past their registered date

ProjectBuiltRegisteredPast dateUnits
Sobha Creek Vistas HeightsSobha Hartland43%no date—1,342
Sobha OneRas Al Khor41%no date—3,028
350 Riverside CrescentBukadra32%no date—742
330 Riverside CrescentBukadra31%no date—758
320 Riverside CrescentBukadra31%no date—630
340 Riverside CrescentBukadra31%no date—760
Verde by SobhaJumeirah Lake Towers27%Jun 2027in 11 mo606
Sobha Seahaven Tower ADubai Harbour22%Apr 2028in 21 mo330
310 Riverside CrescentBukadra22%no date—894
360 Riverside CrescentBukadra20%no date—891
Sobha Seahaven Tower B & CDubai Harbour16%Oct 2028in 27 mo447
SkyscapeBukadra12%Dec 2029in 41 mo1,845
Sobha OrbisMotor City6%Dec 2028in 29 mo2,964
Sobha SolisMotor City4%Dec 2028in 29 mo2,310
Sobha Central Phase IIJumeirah Lake Towers0%Jun 2030in 47 mo2,142
Sobha Central Phase IJumeirah Lake Towers0%Jun 2030in 47 mo2,383
SkyvueBukadra0%Mar 2030in 44 mo2,708
The Element at Sobha OneRas Al Khor0%Dec 2029in 41 mo398

Built % and dates from the DLD register, Jul 2026 · months past date at that register date · a live project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be

Delivered projects, most recent first14 completed; the median measurable completion came 1 month early

Show the 14 delivered projects
ProjectRegisteredCompletedSlippage, months
Sobha Hartland Waves OpulenceSobha HartlandSept 2026Aug 2026-1
Sobha Hartland - Crest GrandeSobha HartlandJun 2026Apr 2026-2
Sobha Hartland - The CrestSobha HartlandDec 2025Dec 2025stamped
Sobha Creek Vistas GrandeSobha HartlandJul 2025Jul 2025stamped
The S TowerDubai Media CityJun 2025Jun 2025stamped
Sobha Hartland Waves GrandeSobha HartlandOct 2023Oct 2024+12
Sobha Hartland WavesSobha HartlandMar 2024Mar 2024stamped
Sobha Creek vistas ReserveSobha HartlandAug 2023Aug 2023stamped
Sobha Hartland One Park AvenueSobha HartlandApr 2023Sept 2022-7
Sobha Creek VistasSobha HartlandJan 2022Dec 2021-1
Sobha Hartland Estates - TownhousesMohammed Bin Rashid CitySept 2021Sept 2021stamped
Sobha Hartland Greens - Phase IIISobha HartlandJan 2021Jan 2021stamped
Sobha Hartland Greens Phase IISobha HartlandJan 2020Jan 2020stamped
Sobha Hartland Greens- Phase ISobha HartlandSept 2018Sept 2018on time

Slippage is months from the registered date to the recorded one; negative is early. The register dates 8 of these 14 completions to the registered day exactly — it writes the completion date onto the planned one — so those are marked “stamped” and left out of the median rather than counted as on time.

Sobha towers on the marketIts towers trade between AED 1,362 and 4,500 per sqft

BuildingMedian price, last 12 monthsSalesFollow
Skyvue AltierBukadraAED 2.19MAED 3,010/sqft431
The Tranquil at Sobha CentralJumeirah Lake TowersAED 2.22MAED 2,975/sqft401
The Serene at Sobha CentralJumeirah Lake TowersAED 2.49MAED 2,975/sqft381
The Horizon at Sobha CentralJumeirah Lake TowersAED 2.66MAED 2,815/sqft258
Sobha Solis Tower BMotor CityAED 1.11MAED 2,015/sqft194
Sobha Hartland - Crest GrandeSobha HartlandAED 2.70MAED 1,952/sqft5.2% gross yield190
The Eden at Sobha CentralJumeirah Lake TowersAED 2.13MAED 2,905/sqft189
Sobha Solis Tower CMotor CityAED 1.10MAED 2,015/sqft158

Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 60+

Every project the Dubai Land Department registers to Sobha, matched by the developer licence number on each registration — a high-confidence identity.

Common questions

Are Sobha's off-plan projects on time?
0 of Sobha's 10 dated live projects are past the completion date the developer registered itself (0%), against 13% across the 28 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-07-06.
How does Sobha rank against other Dubai developers on delivery?
Sobha ranks 4th of the 22 developers ranked on delivery, fewest live projects past their registered date first. Only developers with at least 5 live projects are ranked. Dubai Land Department project register to 2026-07-06.
How late are Sobha's completed projects, typically?
The median measurable completion finished 1 month before its registered date, over 6 completions; 83% of those landed on or before it. 8 more completions were dated to the registered day exactly, where no slippage is observable, and are excluded. Dubai Land Department project register to 2026-07-06.
How many projects has Sobha registered in Dubai?
32 registered projects: 18 live, 14 completed. Projects are matched to Sobha by the developer licence number on each registration. Dubai Land Department project register to 2026-07-06.
What do Sobha's towers sell for?
Its most-traded tower, Skyvue Altier, sold at a median AED 3,010/sqft across 431 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.

For agents

Send Sobha’s delivery record to a client

Open plain-text record

Sobha, delivery record

Record type
Developer-level off-plan register record
Data date
Evidence base
32 registered projects, 18 live of which 0 past their registered date, 6 completions with a measurable slippage of 14 completed; DLD project register as of 2026-07-06; identity high-confidence over 1 licensed company
Sources
Dubai Land Department project register
Canonical record