Aura
Registered for handover in Q3 2024 and 99% built in July 2026, 23 months past that date.
Started Nov 2021Registered handover Aug 2024 · overdue
DLD project register, Jul 2026
- Registered villas
- 808
- Escrow
- بنك الإمارات دبي الوطني (ش.م.ع)
Is Aura a safe off-plan buy?In escrow; 99% built and 23 months past its registered handover; no record of off-plan prices
- Is it on schedule?99% built in July 2026, 23 months past its registered August 2024 handover · DLD project register, Jul 202699%Context
- Is my money protected?Payments go to an escrow account at بنك الإمارات دبي الوطني (ش.م.ع), as registered with the Land DepartmentEscrowContext
- Is the price fair?No off-plan sale registered in 12 months to price it onNo record
- Is it selling?No off-plan sale registered in 12 months0Context
- Who is building it?Majid Al Futtaim Communities, licence no. 1228Context
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
How other Tilal Al Ghaf projects are trackingThe nearest-to-finished are all within their registered dates
“Past date”: the registered date has already passed · 1 of 1 live Tilal Al Ghaf projects past theirs · DLD register and inspections, October 2026
All 4 Tilal Al Ghaf projects →As registered with the Land DepartmentWhere Aura is, and who is on its register row
- Escrow agent
- بنك الإمارات دبي الوطني (ش.م.ع)
- Developer, as licensed
- MAJID AL FUTTAIM TILAL AL GHAF PHASE A L.L.C (no. 1228)
- Master developer
- Majid Al Futtaim Communities
- Registered start
- November 2021
- Configuration
- 808 Townhouses,(G+1+R) & (G+2+R).The project designed to have a concrete structure and block with internal and external finishes.
Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales filed under this project number, 12 months to .
Ask about Aura
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will Aura be completed?
- The developer registered handover for August 2024; that date has passed with no completion recorded, 23 months on, and the project was 99% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
- Is Aura in escrow?
- Yes: the Land Department register names بنك الإمارات دبي الوطني (ش.م.ع) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of Aura?
- MAJID AL FUTTAIM TILAL AL GHAF PHASE A L.L.C, licence no. 1228, by the register’s own licence number; the master developer that owns the land is Majid Al Futtaim Communities. Dubai Land Department project register as of July 2026.
- How many villas does Aura have?
- 808 registered villas. Dubai Land Department project register as of July 2026.
Off-plan record for Aura
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 808 registered villas; DLD project register as of 2026-07-06
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record
- /off-plan/villas/dubai/tilal-al-ghaf/aura
Cite as: Dubai Wealth Index. “Aura, off-plan.” Tilal Al Ghaf, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/villas/dubai/tilal-al-ghaf/aura