Continental Lmd

None of Continental Lmd’s 3 dated pending projects is past the completion date it registered itself, against 13% across developers with ten or more registered projects.

Connect your AI assistant
Pending projects past date
0%
0 of 3 dated pending projects
Delivery rank
n/a
Unranked: under 5 pending projects
Median slippage
n/a
3 measurable of 6 completed
Most-traded tower
AED 1.04M
Taiyo Residences · 269 sales in 12 months

Pending projects past their registered date

0%0 of 3

32 developers with ten or more projects: 13%

Damac 0%Continental Lmd 0%Dubai 13%
Registered projects
10
Completed
6
Pending, no registered date
1

Does Continental Lmd deliver on time? No dated pending project is past its own registered date; its most-traded tower sells at a typical AED 1.04M (AED 1,595/sqft)

  1. Are pending projects on time?0 of 3 dated pending projects are past the date Continental Lmd registered; 1 more carries no date0%Context
  2. How does it rank?Not ranked: the ranking needs 5 pending projects, so one slipped project cannot swing the shareNo record
  3. How late, typically?Only 3 completions carry a date distinct from the plan: 3 of 6 were stamped with itNo record
  4. Do its towers trade?Taiyo Residences trades at AED 1,595/sqft on 269 sales, off-plan and ready, in 12 months; 10 of its towers have a sale recordAED 1.04MContext

Ranked on the share of pending projects past their own registered date · fewest first · register Nov 2026

All 32 developers →

Pending projects, most advanced first4 pending projects, none past their registered date

ProjectBuiltRegisteredPast dateUnits
Boutique 23Jaddaf Waterfront65%no daten/a253
La BoutiqueJaddaf Waterfront53%Dec 2026in 1 mo119
The PierMaritime City48%Dec 2026in 1 mo278
Taiyo ResidencesWasl Gate12%Dec 2027in 13 mo379

Built % and dates from the DLD register, Nov 2026 · months past date at that register date · a pending project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be

Delivered projects, most recent first6 completed, 3 dated to the registered day

Show the 6 delivered projects
ProjectRegisteredCompletedSlippage
Rukan 3RukanDec 2022Jul 202643 mo late
Marina LivingDubai MarinaJun 2025Jan 20267 mo late
Rukan ResidenceRukanFeb 2024Feb 2024stamped
RukanRukanJan 2023Jan 2023stamped
Rukan2RukanAug 2022Aug 2022stamped
Continental TowerDubai MarinaApr 2017Oct 201518 mo early

Slippage is months from the registered date to the recorded one; a minus is early. The register dates 3 of these 6 completions to the registered day exactly, it writes the completion date onto the planned one, so those are marked “stamped” and left out of the median rather than counted as on time. 3 measurable completions are too few to publish a median (the floor is 5).

Continental Lmd’s most-traded towersIts towers trade between AED 1,011 and 2,622 per sqft

BuildingMedian priceAED/sqftGross yieldSalesFollow
Taiyo ResidencesWasl GateAED 1.04M1,595n/a269
Rukan - Building BRukanAED 0.56M1,1489.0%32
The PierMaritime CityAED 2.91M2,622n/a28
Rukan - Building ARukanAED 0.57M1,1118.8%24
Continental TowerDubai MarinaAED 2.20M1,6844.8%21
Rukan - Building CRukanAED 0.82M1,0116.1%21
Marina LivingDubai MarinaAED 1.76M2,1035.5%20
Boutique 23Jaddaf WaterfrontAED 0.90M1,831n/a15

Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 10

Every project the Dubai Land Department registers to Continental Lmd, matched by the developer licence number on each registration : a medium-confidence identity.

Common questions

Are Continental Lmd’s off-plan projects on time?
0 of Continental Lmd’s 3 dated pending projects are past the completion date the developer registered itself (0%), against 13% across the 32 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-11-01.
How does Continental Lmd rank against other Dubai developers on delivery?
Continental Lmd is not ranked: it has 4 pending projects, and the ranking needs 5 so that one slipped project cannot swing the share. Dubai Land Department project register to 2026-11-01.
How late are Continental Lmd’s completed projects, typically?
Not enough to say: only 3 of its 6 completed projects carry a completion date distinct from the registered one, so no median slippage is published. Dubai Land Department project register to 2026-11-01.
How many projects has Continental Lmd registered in Dubai?
10 registered projects: 4 pending, 6 completed. Projects are matched to Continental Lmd by the developer licence number on each registration. Dubai Land Department project register to 2026-11-01.
What do Continental Lmd’s towers sell for?
Its most-traded tower, Taiyo Residences, sold at a median AED 1,595/sqft across 269 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.

Send Continental Lmd’s delivery record to a client

Open plain-text record

Continental Lmd, delivery record

Record type
Developer-level off-plan register record
Data date
Evidence base
10 registered projects, 4 pending, of which 0 past their registered date, 3 completions with a measurable slippage of 6 completed; DLD project register as of 2026-11-01; identity medium-confidence over 1 licensed company
Sources
Dubai Land Department project register
Canonical record
/developers/continental-lmd
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Continental Lmd, delivery record.” Register to 2026-11-01, data to 2026-11-02. https://dubaiwealthindex.com/developers/continental-lmd