Jumeirah Village Triangle

60 registered projects · 30 live, 9,516 units · launches 2009–2026

3 of Jumeirah Village Triangle’s 22 dated live projects (14%) are past their registered completion date. The median live project is 3% built, and 9 more are due within 12 months.

Live projects past their registered date

14%

Past date
3 of 22 dated
Median built, live projects
3%
Due within 12 months
9
Units not yet titled
9,516

Leaders

Most advanced
Altai Tower· 98%
Latest handover
Lilium Tower· Oct 2026
Biggest launch gain
Maya Residences 5· +63.4%

Launch vs resale, development by development-7.1% from launch to resale across Jumeirah Village Triangle: AED 1,527 a sqft at launch, 1,419 on resale

DevelopmentLaunch AED/sqftResale AED/sqftPrice gainRegister
Maya Residences 584963 sales, 2024–251,4389 in 12 mo+69.3%over 1.7 yrsApr 2025handed over
ZaZEN One9258 sales, 20221,3823 in 12 mo+49.4%over 4.3 yrsDec 2021handed over
Green Park66911 sales, 2012–1392212 in 12 mo+37.9%over 12.7 yrsNov 2013handed over
Terhab Hotel & Towers at Jumeirah Village Triangle1,664639 sales, 2016–242,25079 in 12 mo+35.2%over 8.6 yrsNov 2021handed over
The Ivy1,052238 sales, 2022–241,33317 in 12 mo+26.7%over 3.1 yrsJul 2024handed over
CLOUD Tower1,161415 sales, 2022–251,44465 in 12 mo+24.3%over 1.3 yrsNov 2025handed over
Edmonton Elm720101 sales, 2013–2386614 in 12 mo+20.2%over 10.4 yrsMay 2021handed over
Taraf 2 Residence93856 sales, 2022–231,1168 in 12 mo+19.0%over 3.9 yrsJan 2023handed over
Seslia Tower1,177391 sales, 2023–261,3299 in 12 mo+12.9%over 1.9 yrsJul 2026handed over
555 Park Views1,19367 sales, 20241,3349 in 12 mo+11.8%over 1.9 yrsMay 2025handed over
Bali Residences1,210159 sales, 2023–251,34111 in 12 mo+10.8%over 1.8 yrsDec 2023handed over
The Community1,375338 sales, 2017–251,50365 in 12 mo+9.3%over 2.2 yrsSept 2024handed over
Park One93337 sales, 2017–181,0044 in 12 mo+7.6%over 8.6 yrsApr 2018handed over
The One at Jumeirah Village Triangle3,412528 sales, 2016–253,63337 in 12 mo+6.5%over 5.6 yrsJan 2022handed over
Al Manarah Tower999224 sales, 2016–181,04522 in 12 mo+4.6%over 8.8 yrsNov 2017handed over
Milestone Residences1,35542 sales, 2024–261,39727 in 12 mo+3.1%over 1.0 yrsFeb 2026handed over
Emerald Vision Tower1,48334 sales, 2024–251,51516 in 12 mo+2.1%over 0.9 yrsSept 2025handed over
Tranquil Wellness Tower1,51094 sales, 2023–251,51013 in 12 mo0.0%over 2.5 yrsSept 2025handed over
Al Jawhara Tower1,155322 sales, 2017–241,14535 in 12 mo-0.9%over 8.3 yrsMar 2020handed over
Imperial Residence1,019284 sales, 2009–141,00538 in 12 mo-1.4%over 16.5 yrsJun 2014handed over
All of Jumeirah Village Triangleevery building with a launch sale1,52712,842 sales, 2009–261,419520 in 12 mo-7.1%over 1.2 yrs

Survivors only, unpaired, before costs: the all-time median off-plan price per sq ft against ready resales in the 12 months to 12 Oct 2026, pooled across each development’s towers. A median needs 3 sales. Register: construction as the DLD register or a later inspection records it; “past date” means its registered completion month has passed, register Jul 2026. · Showing 20 of 64 rows

Jumeirah Village Triangle sales →

Handover calendar, by registered completion quarterJumeirah Village Triangle: 6,415 apartments planned for 2026–2028, 227% of the homes let there today

Handover calendar

Apartment units, by planned completion quarter

  1. Late: 603
  2. Q4 ’26: 565
  3. Q1 ’27: 335
  4. Q2 ’27: 838
  5. Q3 ’27: 998
  6. Q4 ’27: 721
  7. Q1 ’28: 746
  8. Q2 ’28: 0
  9. Q3 ’28: 1.5k
  10. Q4 ’28: 560
  11. No date: 2.7k
Counted against 18 Oct 2026. Grey: late (planned date passed), after the three-year window, or no date. Source: DLD project and unit registers.

A planned date is the developer’s, not a delivery forecast

Jumeirah Village Triangle supply by year →

Every project in Jumeirah Village Triangle60 off-plan projects, A to Z

60 projects

A

B

C

E

F

G

I

L

M

P

R

S

T

V

W

Z

0–9

Construction progress as the DLD register or a later inspection records it · “past date”: live, and its registered completion month has passed · “no date”: the register gives none · “cancelled”: cancelled in the register · “titled”: complete, with that share of unit titles issued

Back to top ↑

Off-plan apartment record for Jumeirah Village Triangle

Record type
Area-level off-plan delivery record
Data date
Evidence base
60 registered projects, 30 live; 26 buildings with launch and resale evidence
Sources
Dubai Land Department project register and sale transactions
Canonical record
/off-plan/apartments/dubai/jumeirah-village-triangle
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Off-plan apartments in Jumeirah Village Triangle.” Project register to 2026-07-06, sales to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/jumeirah-village-triangle

Source: Dubai Land Department project register () and sale transactions (to ).