Emaar Dubai South
None of Emaar Dubai South’s 14 dated live projects is past the completion date it registered itself: 0%, against 13% across the 28 Dubai developers with ten or more registered projects. Its most-traded tower, Golf Hills 2, registered 180 sales in the last 12 months at a median AED 1.53M (AED 1,587/sqft).
Live projects past their registered date
0%0 of 14
28 developers with ten or more projects: 13%
- Registered projects
- 27
- Completed
- 10
- Live, no registered date
- 3
Does Emaar Dubai South deliver on time?No dated live project is past its own registered date; its most-traded tower sells at a typical AED 1.53M (AED 1,587/sqft)
- Are live projects on time?0 of 14 dated live projects are past the date Emaar Dubai South registered; 3 more carry no date0%Context
- How does it rank?5th of the 22 developers ranked on delivery, fewest overdue first; Dubai’s share past date is 13%5thContext
- How late, typically?Only 1 completion carries a date distinct from the plan: 9 of 10 were stamped with itNo record
- Do its towers trade?Golf Hills 2 trades at AED 1,587/sqft on 180 sales, off-plan and ready, in 12 months; 11 of its towers have a sale recordAED 1.53MContext
Ranked on the share of live projects past their own registered date · fewest first · register Jul 2026
Live projects, most advanced first17 live projects, none past their registered date
Built % and dates from the DLD register, Jul 2026 · months past date at that register date · a live project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be
Delivered projects, most recent first10 completed, 9 dated to the registered day
Show the 10 delivered projectsHide the delivered projects
Slippage is months from the registered date to the recorded one; negative is early. The register dates 9 of these 10 completions to the registered day exactly — it writes the completion date onto the planned one — so those are marked “stamped” and left out of the median rather than counted as on time. 1 measurable completion is too few to publish a median (the floor is 5).
Emaar Dubai South towers on the marketIts towers trade between AED 1,294 and 1,932 per sqft
Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 11
Every project the Dubai Land Department registers to Emaar Dubai South, matched by the developer licence number on each registration — a high-confidence identity.
Common questions
- Are Emaar Dubai South's off-plan projects on time?
- 0 of Emaar Dubai South's 14 dated live projects are past the completion date the developer registered itself (0%), against 13% across the 28 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-07-06.
- How does Emaar Dubai South rank against other Dubai developers on delivery?
- Emaar Dubai South ranks 5th of the 22 developers ranked on delivery, fewest live projects past their registered date first. Only developers with at least 5 live projects are ranked. Dubai Land Department project register to 2026-07-06.
- How late are Emaar Dubai South's completed projects, typically?
- Not enough to say: only 1 of its 10 completed projects carries a completion date distinct from the registered one, so no median slippage is published. Dubai Land Department project register to 2026-07-06.
- How many projects has Emaar Dubai South registered in Dubai?
- 27 registered projects: 17 live, 10 completed. Projects are matched to Emaar Dubai South by the developer licence number on each registration. Dubai Land Department project register to 2026-07-06.
- What do Emaar Dubai South's towers sell for?
- Its most-traded tower, Golf Hills 2, sold at a median AED 1,587/sqft across 180 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.
For agents
Send Emaar Dubai South’s delivery record to a client
Emaar Dubai South, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 27 registered projects, 17 live of which 0 past their registered date, 1 completions with a measurable slippage of 10 completed; DLD project register as of 2026-07-06; identity high-confidence over 1 licensed company
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/emaar-dubai-south
Cite as: Dubai Wealth Index. “Emaar Dubai South, delivery record.” Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/developers/emaar-dubai-south