Greenville
Registered for handover in Q1 2029 and 1% built in July 2026.
Started Jan 2025Registered handover Mar 2029
DLD project register, Jul 2026
- Registered villas
- 140
- Escrow
- بنك ابوظبى التجارى
Is Greenville a safe off-plan buy?In escrow; 1% built with 32 months to its registered handover; no record of off-plan prices
- Is it on schedule?1% built in July 2026 against a March 2029 handover: 99% left to build in 32 months · DLD project register, Jul 20261%Context
- Is my money protected?Payments go to an escrow account at بنك ابوظبى التجارى, as registered with the Land DepartmentEscrowContext
- Is the price fair?No off-plan sale registered in 12 months to price it onNo record
- Is it selling?No off-plan sale registered in 12 months0Context
- Who is building it?Emaar Dubai South, licence no. 1155; 0 of its 14 dated live projects are past their registered dates0%Context
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
How other Dubai South projects are trackingThe nearest-to-finished are all past their registered dates
“Past date”: the registered date has already passed · 3 of 15 live Dubai South projects past theirs · DLD register and inspections, October 2026
All 33 Dubai South projects →As registered with the Land DepartmentWhere Greenville is, and who is on its register row
- Escrow agent
- بنك ابوظبى التجارى
- Developer, as licensed
- EMAAR DUBAI SOUTH DWC LLC (no. 1155)
- Master developer
- Emaar Dubai South
- Registered start
- January 2025
- Configuration
- Freehold G+1 Townhouses consisting of 70 nos. of 3Bedroom and 70 nos. of 4Bedroom
Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales filed under this project number, 12 months to .
More from Emaar Dubai South
Live projects registered to the same developer, most advanced first.
Ask about Greenville
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will Greenville be completed?
- The developer registered handover for March 2029, 32 months after DLD’s latest record, and the project was 1% built as of July 2026. A registered date is the developer’s own, not a delivery forecast. Dubai Land Department project register as of July 2026.
- Is Greenville in escrow?
- Yes: the Land Department register names بنك ابوظبى التجارى as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of Greenville?
- EMAAR DUBAI SOUTH DWC LLC, licence no. 1155, by the register’s own licence number; the master developer that owns the land is Emaar Dubai South. Dubai Land Department project register as of July 2026.
- How many villas does Greenville have?
- 140 registered villas. Dubai Land Department project register as of July 2026.
Off-plan record for Greenville
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 140 registered villas; DLD project register as of 2026-07-06
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
- Canonical record
- /off-plan/villas/dubai/dubai-south/greenville
Cite as: Dubai Wealth Index. “Greenville, off-plan.” Dubai South, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/villas/dubai/dubai-south/greenville