Data to
Iman
1 of Iman’s 8 dated pending projects is past the completion date it registered itself, against 13% across developers with ten or more registered projects.
- Pending projects past date
- 13%
- 1 of 8 dated pending projects
- Delivery rank
- 16th
- of 26 ranked developers, fewest overdue first
- Median slippage
- n/a
- 2 measurable of 8 completed
- Most-traded tower
- AED 1.31M
- Sierra by Iman · 544 sales in 12 months
Pending projects past their registered date
13%1 of 8
32 developers with ten or more projects: 13%
- Registered projects
- 17
- Completed
- 8
- Pending, no registered date
- 1
Does Iman deliver on time? Fewer of its pending projects are past their own dates than Dubai’s share; its most-traded tower sells at a typical AED 1.31M (AED 1,680/sqft)
- Are pending projects on time?1 of 8 dated pending projects is past the date Iman registered; 1 more carries no date13%Context
- How does it rank?16th of the 26 developers ranked on delivery (those with 5 or more pending projects), fewest overdue first; Dubai’s share past date is 13% across all 32 developers with ten or more projects16thContext
- How late, typically?Only 2 completions carry a date distinct from the plan: 6 of 8 were stamped with itNo record
- Do its towers trade?Sierra by Iman trades at AED 1,680/sqft on 544 sales, off-plan and ready, in 12 months; 17 of its towers have a sale recordAED 1.31MContext
Ranked on the share of pending projects past their own registered date · fewest first · register Nov 2026
Pending projects, most advanced firstGardens 2 is 68% built and 11 months past its date
Built % and dates from the DLD register, Nov 2026 · months past date at that register date · a pending project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be
Delivered projects, most recent first8 completed, 6 dated to the registered day
Show the 8 delivered projectsHide the delivered projects
Slippage is months from the registered date to the recorded one; a minus is early. The register dates 6 of these 8 completions to the registered day exactly, it writes the completion date onto the planned one, so those are marked “stamped” and left out of the median rather than counted as on time. 2 measurable completions are too few to publish a median (the floor is 5).
Iman’s most-traded towersIts towers trade between AED 1,340 and 2,758 per sqft
Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 17
Every project the Dubai Land Department registers to Iman, matched by the developer licence number on each registration : a medium-confidence identity.
Common questions
- Are Iman’s off-plan projects on time?
- 1 of Iman’s 8 dated pending projects is past the completion date the developer registered itself (13%), against 13% across the 32 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-11-01.
- How does Iman rank against other Dubai developers on delivery?
- Iman ranks 16th of the 26 developers ranked on delivery, fewest pending projects past their registered date first. Only developers with at least 5 pending projects are ranked. Dubai Land Department project register to 2026-11-01.
- How late are Iman’s completed projects, typically?
- Not enough to say: only 2 of its 8 completed projects carry a completion date distinct from the registered one, so no median slippage is published. Dubai Land Department project register to 2026-11-01.
- How many projects has Iman registered in Dubai?
- 17 registered projects: 9 pending, 8 completed. Projects are matched to Iman by the developer licence number on each registration. Dubai Land Department project register to 2026-11-01.
- What do Iman’s towers sell for?
- Its most-traded tower, Sierra by Iman, sold at a median AED 1,680/sqft across 544 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.
Send Iman’s delivery record to a client
Open plain-text recordIman, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 17 registered projects, 9 pending, of which 1 past their registered date, 2 completions with a measurable slippage of 8 completed; DLD project register as of 2026-11-01; identity medium-confidence over 1 licensed company
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/iman
Cite as: Dubai Wealth Index. “Iman, delivery record.” Register to 2026-11-01, data to 2026-11-02. https://dubaiwealthindex.com/developers/iman